1. General requirements for labor protection

Only males at least 18 years of age who have the appropriate qualifications confirmed by a certificate, who have studied the design features and rules for the safe operation of this mechanism, and who have completed a preliminary medical examination with a permit to work at height, are allowed to work with a gasoline-powered tool.

Persons who have passed the test of knowledge on labor protection and fire safety are allowed to work.

All newly hired workers for two to six shifts (depending on the nature of the work) must work under the supervision of a foreman or experienced worker.

Hand tools (axes, scythes, shovels, scissors, felling forks, etc.) must be fixed, have honed working parts and correctly fitted and strong handles without roughness and cracks.

Felling trees is prohibited:

  • on heavily snow-covered slopes with the threat of landslides;
  • in case of snowfall, fog (when visibility is less than 50 m; wind force more than 5 points;
  • with a wind of 7 points or more, the stay of workers in the plantations is prohibited.

Felling trees without felling devices is prohibited.

All workers, specialists involved in felling forests must wear protective helmets. Work without protective helmets is prohibited.

During a thunderstorm, working personnel should not be under the crowns of tall trees, near masts and other structures that can be struck by lightning.

It is forbidden for people to approach energized and unprotected wires or parts of the contact network at a distance of less than 2 m, as well as touching the electrical equipment of the electric rolling stock, both directly and through any objects.

If it is necessary to approach, according to the conditions of work, to energized and not fenced parts of the contact network and overhead lines, as well as related devices, the voltage must be removed and grounding must be established for the entire period of work.

It is forbidden to approach closer than 8 m to broken wires of overhead lines and contact network.

2. Labor protection requirements before starting work

The foreman who led the team is obliged, before starting work, with each change in the conditions and nature of the work, to conduct a targeted briefing against the signature of the workers, which indicates, in relation to local conditions, all safety measures for the workers.

A first aid kit with a set of medicines for providing first aid, medical aid, must always be in the places of work, on tractors and cars.

Before going to work, the foreman, the head of the site is obliged to check the serviceability of the tools, machines, mechanisms and necessary devices, the availability and condition of overalls and personal protective equipment, conduct a briefing on labor protection, familiarize the workers with the route of safe passage to the place of work and back.

Before the start of the shift, the foreman examines the upcoming work area. In places where the underground cable passes and dangerous bridges (stumps, large stones, pits, cliffs), milestone signs of such a height are installed so that they are visible.

Plantations in which trees are felled manually or by tractor units (pendulum saw), as well as shrubs are cut with a tractor disk brush cutter, are a dangerous zone. The place for felling trees and cutting shrubs is fenced at a distance of 50 m with a portable standard prohibition sign with the inscription "Danger zone. Passage is FORBIDDEN."

Work on thinning and sanitary felling of forests, including felling trees, must be carried out in accordance with the approved technological map. After getting acquainted with it, the team is given a diagram of the cutting area being developed, which indicates the order of execution: work, danger zones, arrangement of mechanisms and equipment, technological elements of the cutting area, safety equipment. The feller of the forest, his assistant and other members of the team must follow the established technology and this instruction on labor protection, before starting work, make sure of their knowledge, clarify any unclear questions with the foreman and not deviate from the established technology without the knowledge of the foreman.

Do not start felling trees without] confidence that there are no dangerous trees and other dangerous factors in the cutting area, which can lead to injury or an accident.

If you find any malfunctions of the chainsaw and it is impossible to fix them on your own, inform the master. Do not start working with faulty: saw, equipment, mechanisms, hand tools.

Prior to the felling of a tree, a workplace must be prepared:

  • around the tree, within a radius of at least 0,7 m, a shrub that interferes with felling is cut;
  • at an angle of 60 degrees to the direction of the felling of the tree, escape routes (paths) are made;
  • in the direction opposite to the direction of the felling, not less than 3 m long (and, if necessary, 2 or more tracks) and not less than 0,45 m wide.

In winter, snow is removed around the tree and escape routes, after it is trampled down, a layer no more than 0,2 m thick is left on the ring and 0,3 m on the paths. In addition to shrubs, other obstacles that interfere with the felling of trees are removed.

Before starting work, make sure that there are no unauthorized persons and equipment in the cutting area, and that hazardous areas are fenced off.

3. Labor protection requirements during work

When performing work, it is necessary to use appropriate overalls, safety shoes, and other PPE (assembly belt, protective helmet, gloves or gloves, goggles or protective shield, noise protection equipment).

The foreman (head of the site) is obliged to warn all members of the team before starting work about the danger of falling trees, ropes, etc. approaching the power lines.

If it is necessary to approach, according to the conditions of the work - cutting trees - to the unprotected parts of the COP and VL, which are under voltage, at a distance of less than 2 m, the contact network, overhead power line and devices connected to them must be de-energized and grounded for the entire period of work.

To do this, the manager (head of the section, foreman; is obliged to give a written application to the head of the power supply distance and the senior energy dispatcher about the need to ensure the production of work near the devices of the contact network or overhead power line, indicating the exact location, start, duration and content of the work, as well as inform about this to the head of the relevant ECHK or EChS. For scheduled work, such an application is submitted at least XNUMX hours in advance.

The head of the EChS (EChS), on the basis of the application of the head of work of PChL-1, appoints by order from among the employees who are part of the EChS (EChS), responsible for

electrical safety in the part of the CS and VL (hereinafter responsible) whose name is reported in advance to the energy dispatcher and the work manager of PChL-1.

Responsible ECHK (EPS) supervises the compliance of employees with electrical safety requirements. Its requirements on electrical safety are mandatory for the supervisor to perform.

Works related to signaling devices are carried out with the participation of a signaling electrician whose requirements are mandatory for the work manager.

Upon arrival at the work site, the responsible EChK (ES) contacts the energy dispatcher, receives a verbal order from him (via the established means of communication), allowing the work to be carried out, and performs grounding along the entire front determined by the work foreman.

In the absence of communication between the responsible ECHK (ESHS) and the energy dispatcher, work does not start. In case of violation after the start of work, the connection between the responsible ECHK (ES) and the energy dispatcher, the work is stopped until the connection is restored.

After installing the grounding, the responsible EChK (ES) gives the work manager a written permission to work in the form, according to the appendix (permit form

attached to this manual), on the possibility of starting work, indicating the number of the order of the energy dispatcher, the start and end time of work. A copy of the permit remains with the responsible person.

It is strictly forbidden to start work under power lines without a representative of the power supply distance!

It is forbidden to touch the broken wires of the COP and VL and objects that touch them.

The distance from the extreme wires of the overhead line to the crown of trees in parks, forest plantations should be at least: 2 m for overhead lines with a voltage of up to 20 kV, 3 m for an overhead line with a voltage of 35-110 kV, 4 m - for an overhead line with a voltage of 150-200 kV.

Responsible for the general state of labor protection is the person who leads the team of these workers and is constantly at the workplace.

The distance between individual groups of workers engaged in felling trees must be at least 50 m.

Climbing onto supports, approaching or touching trees, ropes, etc. is not allowed. with VL wires.

In order to avoid an unexpected fall of trees, first of all, it is necessary to dump rotten, burnt and fragile trees.

Felling of trees should be carried out after sawing or cutting, the depth of which in upright trees is at least a quarter of the thickness of the butt. A notch or undercut is performed from the side where the tree is to be felled. The lower plane of the notch or undercut should be perpendicular to the axis of the tree, and its upper side should form an angle of 35 - 400 with the lower plane.

The cutting plane must be higher than the bottom plane of the undercut. The saw cut of a tree should be performed from the side opposite to the undercut or undercut.

The saw cut should not reach the edge of the cut for healthy trees by 2-3 cm, for dead and rotten trees - by 4-5 cm. It is prohibited to fell trees without a cut or cut. It is forbidden to make through. sawed wood. Inclined trees should be felled in the direction of their slope.

If, after the end of the cut, the tree begins to fall, it is necessary to resort to forced felling, for example, to drive a wedge into the cut. Before felling rotten and dead trees, one should test their strength with a pole and make a notch instead of a cut.

In the event of a tree falling onto the wires, it is forbidden to approach the tree at a distance of less than 8 m until the voltage is removed from the overhead line.

The feller must warn other workers about the upcoming fall of the felled tree. Standing on the side of the fall of the tree and on the opposite side is prohibited. In order to prevent trees from falling on the wires, guys should be applied in the direction opposite to the wires. Guys should be installed before cutting the tree. Guys must be secured to a tree or other stable object.

4. Labor protection requirements at the end of work

Upon completion of work, the work manager is obliged to check that all people are removed from parts of the COP at a distance of more than 2 m, and then mark the time of completion of work on a copy of the written permission (in the "Notification" section) held by the responsible EChK. The responsible ECHK, having personally made sure that all people are at a safe distance, removes the ground rods and notifies the energy dispatcher about this. After removing the grounding rods, the COP is considered energized and it is forbidden to approach it. After work, copies of the "Permission" and "Notice" are stored in the ECHK for a month.

Any work on the wires crossing the CS is prohibited without removing the voltage from the CS and grounding it.

All work on the COP, overhead lines and related devices during a thunderstorm, as well as when it approaches, is prohibited.

In electrified areas of direct and alternating current, cutting down trees located at a distance of 2 to 10 meters from live parts of the CS and VL can be carried out without de-energizing and grounding the CS and VL under the supervision of a specially appointed representative of the power supply distance.

It is forbidden to leave a felled or sawn tree unfelled during a break in work or when moving to other trees.

It is forbidden for PSL employees to cut down trees and shrubs and mow poles and electric masts within a radius of 1 meter from the edge of the pole.

5. Labor protection requirements in emergency situations

In the event of a fire, immediately inform the fire department by calling _______.

Regardless of the call to the fire brigade, in the event of a fire, measures must be taken to extinguish the fire.

Extinguishing of burning objects located at a distance of less than 2 m from the CS is allowed to be carried out only after preliminary de-energization and grounding of the CS in the prescribed manner, upon receipt of a written permit from the responsible EChK, EChS to carry out fire extinguishing.

Extinguishing burning objects located at a distance of more than 7 m from the COP, which is energized, can be allowed without removing the voltage.

In this case, it is necessary to ensure that the jet of water or foam does not approach at a distance of less than 2 m from the CS and other parts under voltage.

See other articles Section Occupational Safety and Health

 We recommend interesting articles Section Standard instructions for labor protection:

▪ Thermal insulation insulator. Standard instruction on labor protection

▪ Test preparation. Standard instruction on labor protection

▪ Work on cassette-knife folding machines. Standard instruction on labor protection

See other articles Section Standard instructions for labor protection.

Read and write useful comments on this article.

<< Back

Latest news of science and technology, new electronics:

Artificial leather for touch emulation 15.04.2024

In a modern technology world where distance is becoming increasingly commonplace, maintaining connection and a sense of closeness is important. Recent developments in artificial skin by German scientists from Saarland University represent a new era in virtual interactions. German researchers from Saarland University have developed ultra-thin films that can transmit the sensation of touch over a distance. This cutting-edge technology provides new opportunities for virtual communication, especially for those who find themselves far from their loved ones. The ultra-thin films developed by the researchers, just 50 micrometers thick, can be integrated into textiles and worn like a second skin. These films act as sensors that recognize tactile signals from mom or dad, and as actuators that transmit these movements to the baby. Parents' touch to the fabric activates sensors that react to pressure and deform the ultra-thin film. This ... >>

Petgugu Global cat litter 15.04.2024

Taking care of pets can often be a challenge, especially when it comes to keeping your home clean. A new interesting solution from the Petgugu Global startup has been presented, which will make life easier for cat owners and help them keep their home perfectly clean and tidy. Startup Petgugu Global has unveiled a unique cat toilet that can automatically flush feces, keeping your home clean and fresh. This innovative device is equipped with various smart sensors that monitor your pet's toilet activity and activate to automatically clean after use. The device connects to the sewer system and ensures efficient waste removal without the need for intervention from the owner. Additionally, the toilet has a large flushable storage capacity, making it ideal for multi-cat households. The Petgugu cat litter bowl is designed for use with water-soluble litters and offers a range of additional ... >>

The attractiveness of caring men 14.04.2024

The stereotype that women prefer "bad boys" has long been widespread. However, recent research conducted by British scientists from Monash University offers a new perspective on this issue. They looked at how women responded to men's emotional responsibility and willingness to help others. The study's findings could change our understanding of what makes men attractive to women. A study conducted by scientists from Monash University leads to new findings about men's attractiveness to women. In the experiment, women were shown photographs of men with brief stories about their behavior in various situations, including their reaction to an encounter with a homeless person. Some of the men ignored the homeless man, while others helped him, such as buying him food. A study found that men who showed empathy and kindness were more attractive to women compared to men who showed empathy and kindness. ... >>

Random news from the Archive

Purifier Generator 24.03.2015

Bacteria, purifying water, will give electricity. As a rule, wastewater treatment is a costly process, but it can also be made a little profitable.

For example, those organic substances from which water is purified have stored a lot of energy in their chemical bonds. If they are simply decomposed, the energy will be lost. But if special bacteria do this, which in the process of feeding will create a pair of proton and electron, and if these bacteria are also placed on an electrode through which they can give their electron to the circuit, then chemical energy will turn into electrical energy.

This idea is not new, many researchers have taken on the creation of a bacterial fuel cell, but few have come up with something worthwhile. Another attempt was made by Luis Cesar Colminares and Roman Netzer: working on the project of the Norwegian innovation center SINTEF, they created a cell for wastewater treatment.

The researchers took a long time to select cultures of bacteria and eventually succeeded: the laboratory setup is able to provide enough electricity to power a small fan. Wastewater comes from a nearby dairy farm and is saturated with organic acids that bacteria love. However, the battery must also work on water of a different composition.'

"We don't expect to produce much electricity, but our plant is cheap and the purification process is energy-intensive," says Netzer.

Other interesting news:

▪ Bananas under threat

▪ Super glue will close wounds in the stomach and stop the leakage of acids in the plant

▪ Special beer for air travel

▪ A new type of tectonic activity has been discovered on Venus

▪ Implant LEDs Control Brain Functions

News feed of science and technology, new electronics

 

Interesting materials of the Free Technical Library:

▪ section of the site Lecture notes, cheat sheets. Selection of articles

▪ Article Welfare State. Popular expression

▪ article Which mathematician accurately predicted the day of his death using an arithmetic progression? Detailed answer

▪ article Snow plow driver. Standard instruction on labor protection

▪ article ATX-compatible computer power supply for the car. Encyclopedia of radio electronics and electrical engineering

▪ article Voltage level deviation LED indicator. Encyclopedia of radio electronics and electrical engineering

Leave your comment on this article:

Name:


Email (optional):


A comment:





All languages ​​of this page

Home page | Library | Articles | Website map | Site Reviews

www.diagram.com.ua

www.diagram.com.ua
2000-2024