1. General provisions

1.1. The instruction on labor protection (hereinafter referred to as the instruction) was developed in accordance with the requirements of the Law of Ukraine "On labor protection" and establishes the rules for the performance of work and the behavior of an employee on the territory of the enterprise, in production premises and at the workplace in accordance with state, intersectoral and sectoral regulations about labor protection.

1.2. The instructions apply to all departments of the enterprise.

1.3. In accordance with Article 18 of the Law of Ukraine "On Labor Protection", an employee is obliged to know and comply with the requirements of regulatory acts on labor protection, the rules for handling machines, mechanisms, equipment and other means of production, use collective and individual protective equipment, undergo preliminary and periodic medical examinations.

1.4. Depending on the specific conditions of the organization of the production process, as well as in connection with the accidents and accidents, the instructions may be amended and supplemented, which are set out on a separate sheet signed by the head of the relevant structural unit.

1.5. The instruction is a mandatory normative document for the driver of a mobile plastering station.

1.6. Persons at least 18 years of age who have undergone a medical examination, special training, instructing at the workplace and received a certificate for the right to operate the station, are familiar with the operating instructions, are allowed to operate the mobile plastering station.

1.7. The machinist of the plastering station must have a tariff category of at least 4th and an electrical safety group of at least II.

1.9. The driver must undergo the following safety briefings:

a) introductory - when applying for a job;

b) primary - at the workplace;

c) repeated - at least once every 3 months;

d) unscheduled - in case of violation of labor safety requirements, which led or could lead to an accident or an accident; when changing the technological process, the design of the station or the current regulations on labor protection;

e) target - when performing one-time work not directly related to duties in the specialty, liquidating an accident, natural disaster, performing work for which a work permit, permit and other documents are issued.

1.8. Re-testing the knowledge of work safety by the driver (including knowledge of electrical safety requirements with the assignment of group II) is carried out:

a) periodically, not once every 12 months (to the extent of knowledge of this manual);

b) when there is a break in work in the specialty for more than 6 months;

c) before admission to work after the temporary suspension of the driver for violation of safety or technology requirements.

1.9. An additional check of the knowledge of the driver is carried out:

a) when switching to new methods for preparing mixtures or types of work;

b) when preparing mixtures from new materials or with a significant change in the technology of their preparation.

1.10. To reduce the level of influence of hazardous and harmful production factors, the driver must be provided with the following personal protective equipment:

  • cotton overalls - wear period 12 months;
  • rubber boots - wear period 12 months;
  • combined mittens - wearing period 1 month.

On outdoor robots in winter additionally:

  • cotton jacket with insulated lining - wearing period 36 months;
  • cotton trousers with insulated lining - wearing period is 36 months;
  • felt boots - wearing period 48 months.

Depending on the nature and conditions of the work performed, the driver must also use other personal protective equipment (for example, a protective helmet, a respirator, goggles, alkali-resistant rubber gloves, etc.).

1.11. Upon receipt of overalls, safety shoes and other personal protective equipment, the driver must be instructed by the work manager on the procedure for using these means and familiarized with the requirements for caring for them.

1.12. The driver must not start work in unsuitable, contaminated overalls, safety shoes and with faulty safety devices.

1.13. The place of installation of the plastering station at the construction site is determined by the project for the execution of works.

The plastering station should be installed on a planned horizontal surface, outside the danger zone of other working machines and mechanisms, and convenient access roads should be arranged on the loading side (inventory metal overpasses, ramps made of reinforced concrete slabs).

1.14. The driver's workplace must be connected with the places where the mixture is received by sound or light alarms.

1.15. The plaster station must be protected from precipitation by a canopy, and in winter it must be insulated.

1.16. Over flexible mortar pipelines laid in places of constant movement of people or vehicles, it is necessary to install bridges.

1.17. Connecting the plastering station to the mains supply should be carried out using a power point that contains switching and protective devices (a box with fuses or circuit breakers and a knife switch). For connection it is necessary to use cables with aluminum or copper conductors with rubber or plastic insulation.

External electrical wiring of temporary power supply must be placed on supports at a height above the ground, platform, flooring, at least, m:

a) 2,5 - over jobs;

b) 3,5 - over the aisles,

c) 6,0 - over driveways.

1.18. Connection and disconnection of the plaster station, as well as supervision of the good condition of the electrical part of the station during operation, can only be performed by an electrician who has an electrical safety group of at least III.

The driver is not allowed to do this work.

1.19. An insulating stand must be placed at the driver's workplace.

1.20. Screw mixers, screening drums must be equipped with a protective grid, interlocked limit switches with motor starters.

The driver is obliged every day to check the serviceability of the lock - if the engine does not turn on when the protective grille is raised or removed, the lock is working.

1.21. The machinist of the plastering station is obliged:

  • know the device (design), the principle of operation and the rules for the technical operation of the station;
  • be able to troubleshoot basic problems in the mechanical part of the station;
  • observe safety rules when cleaning and lubricating components and assemblies;
  • know the adopted signaling system;
  • operate and maintain the station in accordance with the manufacturer's instructions.

1.22. It is forbidden for the driver to be in a state of intoxication on the territory of the construction site and in the domestic premises both during working and non-working hours.

2. Safety requirements before starting work

2.1. Before starting work, the mobile plastering station operator must:

  • put on overalls, safety shoes and other necessary personal protective equipment;
  • familiarize yourself with the records of the driver of the previous shift in the shift acceptance log;
  • receive an assignment for the performance of work and instructions on labor protection from the foreman (foreman);
  • inspect the workplace, remove foreign objects, check the serviceability of the working tool, prepare and conveniently position it;
  • make sure that there are safe passages with a width of at least 0,6 m, signal fencing of hazardous areas and safety signs on them, sufficient illumination of the workplace.

2.2. Before starting the plastering station, the driver must check:

  • the presence of an insulating stand at the workplace;
  • the absence of foreign objects in the mixing hopper (stones, pieces of metal, etc.), and in the nozzle, pipelines and rubber hoses - the remains of the solution;
  • gap between the auger shovels and the inner surface of the hopper;
  • reliability of tightening threaded connections;
  • availability, serviceability and reliability of fastening of protective fences on rotating parts of the equipment;
  • the presence of lubrication on rubbing surfaces and the oil level in the gearboxes;
  • tension of drive belts;
  • the possibility of free scrolling of the paddle shaft (auger);
  • external inspection - the presence and integrity of the protective grounding of the cases of electric motors and starting devices, the condition of the insulation of electrical wires;
  • the presence of manometers on the mortar pump and seals or stamps on them;
  • the condition of the rubber hoses along the entire length of their attachment to the mortar pump and the tightness of the joints at the joints of the mortar pipeline.

2.3. Before the machinist cleans the receiving hopper of the plastering station from the remnants of the mortar (removing foreign objects), lubricates the rubbing surfaces of the equipment, scrolls the paddle shaft (auger) by hand, tightens the drive belts, the electrician must turn off the breaker, remove the fuses, lock the breaker handle in the off position and put up a poster: "Do not turn it on! People are working!".

It is not allowed to clean the bunker without a specially allocated worker from among the workers of the link (team, section) to ensure the safety of the driver.

2.4. When inspecting a plastering station and performing any repair or maintenance work on it, it is prohibited to disable protective grid devices interlocked with launchers.

2.5. If malfunctions are detected that cannot be eliminated on their own, the driver is obliged to inform the manager responsible for the safe performance of work (mechanic, foreman, foreman) about this.

2.6. After elimination of the identified faults, and also before starting work, it is necessary to check the operation of all components and assemblies of the plastering station at idle (without load), after giving a warning sound signal about this.

3. Safety requirements during work

3.1. The driver must only perform the work for which he has been instructed and approved by the work manager.

3.2. Do not allow people who are not related to this work to the workplace.

3.3. During work, be attentive yourself and not distract others.

3.4. During operation, the driver must ensure that:

  • the mixer was loaded with the engine running;
  • the mass of the loaded solution did not exceed the capacity of the hopper;
  • the loaded solution did not contain foreign objects that could lead to jamming of the auger;
  • the loaded solution was fed into the hopper evenly to avoid jamming of the rotor and its breakage;
  • bearings and gearbox housings did not heat up;
  • the auger blades did not touch the inner surface of the bunker;
  • reception, mixing and dispensing of the solution were carried out in accordance with the requirements of technological maps and established operating modes in winter;
  • the pressure in the mortar pipeline did not exceed 6 kgf/cm2. In case of excess pressure, stop the engine and find out the cause;
  • there was no leakage of the solution in the inventory connections of the mortar pipeline;
  • the water level in the tank with the heating turned on was not lower than the mark on the gauge glass.

3.5. The supply of dump trucks for unloading the solution in reverse is allowed only at the signal of the machinist of the plastering station.

3.6. To clean the mortar pipelines and cavities of the clogged pump with water, having previously relieved the pressure and disconnected the clogged section. This operation must be carried out with the obligatory use of protective goggles.

In order to avoid injury, it is forbidden for the driver to be at the ends of the disconnected links of the mortar pipeline, to direct the ends of the clogged links at people.

3.7. The machinist of the plastering station is prohibited from:

  • operate the station with faulty units, the manometer on the mortar pump, damaged rubber hoses, as well as the formation of plugs in the hoses and nozzle nozzle;
  • work with the guards of the rotating parts of the equipment removed;
  • bend at an acute angle the hoses through which the solution is transported, fix the flexible hoses on the fittings with wire twists - for these purposes it is necessary to use inventory clamps;
  • independently connect (disconnect) the station to (from) the power grid and maintain electrical equipment;
  • disassemble and repair parts of mechanisms on the go, and the mortar pump and rubber hoses - under pressure, as well as tighten (tighten) seals and flange connections under pressure;
  • lubricate and clean mechanisms and troubleshoot during their operation;
  • put hands, a shovel into the bunker, take samples or collect the mixture with the auger turned on;
  • to carry out unloading of dump trucks from a flyover that does not have a serviceable breaking bar;
  • operate the auger installation without a grid interlocked with the auger electric motor on the receiving hopper or when it is not tightly closed;
  • walk along the hopper grate, push through the stuck solution;
  • turn off the electrical interlock, disable limit switches and dead ends;
  • be in the danger zone of the cargo moved by the crane when lifting boxes or hoppers with a solution;
  • reload boxes (bunkers) for solution above the established norm;
  • perform slinging without having a slinger's certificate;
  • transfer control of the station to other workers, as well as leave the working station unattended.

4. Safety requirements after finishing work

4.1. Stop the mortar pump, open the passage device and release the solution from the cap and hoses, turn off the pump and pump out the remaining solution, then rinse the pump and the mortar line with water.

4.2. Remove the cap and suction elbow, clean them from hardened particles of the solution.

4.3. With the onset of frost, be sure to drain the water from the pump, for which it is necessary to unscrew the plug in the lower part of the flange of the pumping chamber, while opening the drain tap.

4.4. Rinse the vibrobunker and screw mixer with water.

4.5. Disconnect the station from the mains, close the switch with a padlock.

4.6. Make an entry in the shift log about the identified malfunctions in the operation of the station, report to the work manager for action.

5. Safety requirements in emergency situations

5.1. In cases of equipment malfunction or in emergency situations that can cause equipment breakdown and injury to people, the plastering station operator must:

  • immediately stop work and disconnect the station from the mains, using the emergency shutdown controls if necessary;
  • Report all malfunctions and the measures taken to eliminate them to the work manager.

5.2. In the event of a fire, turn off the plastering station from the mains, organize fire extinguishing with primary fire extinguishing equipment. Burnt electrical wires should be extinguished with powder or carbon dioxide fire extinguishers.

It is forbidden to extinguish live wires with water, foam fire extinguishers and sand.

If it is impossible to eliminate the source of fire on your own, you must immediately report by phone "01" to the fire department.

5.3. If an accident occurs during work, the driver is obliged to immediately turn off the station and provide first aid to the victim, report the incident to the work manager and take measures to preserve the situation of the accident, if this does not threaten the life and health of people.

5.3. If there are victims, it is necessary to provide them with first aid, if necessary, call an ambulance.

5.4. Providing first aid.

5.4.1. First aid for electric shock.

In case of electric shock, it is necessary to immediately release the victim from the action of electric current by disconnecting the electrical installation from the power source, and if it is impossible to disconnect it, pull it away from the conductive parts by clothing or using insulating material at hand.

If the victim has no breathing and pulse, it is necessary to give him artificial respiration and indirect (external) heart massage, paying attention to the pupils. Dilated pupils indicate a sharp deterioration in the blood circulation of the brain. In this state, the revival must begin immediately, and then call an "ambulance".

5.4.2. First aid for injury.

To provide first aid in case of injury, it is necessary to open an individual package, apply a sterile dressing material, which is placed in it, to the wound and tie it with a bandage.

If somehow the individual package was not found, then a clean handkerchief, a clean linen rag, etc. must be used for dressing. On a rag that is applied directly to the wound, it is advisable to drip a few drops of tincture of iodine to get a stain larger than the wound, and then apply the rag to the wound. It is especially important to apply the tincture of iodine in this way to contaminated wounds.

5.4.3. First aid for fractures, dislocations, shocks.

In case of fractures and dislocations of the limbs, it is necessary to strengthen the damaged limb with a splint, plywood plate, stick, cardboard or other similar object. The injured arm can also be hung with a bandage or handkerchief from the neck and bandaged to the torso.

In case of a skull fracture (unconsciousness after a blow to the head, bleeding from the ears or mouth), it is necessary to apply a cold object to the head (a heating pad with ice, snow or cold water) or make a cold lotion.

If a fracture of the spine is suspected, it is necessary to put the victim on the board, without lifting him, turn the victim on his stomach face down, while observing that the body does not bend, in order to avoid damage to the spinal cord.

In case of a fracture of the ribs, a sign of which is pain during breathing, coughing, sneezing, movements, it is necessary to tightly bandage the chest or pull it off with a towel during exhalation.

5.4.4. First aid for burns with acids and alkalis.

If acid or alkali gets on the skin, the damaged areas must be thoroughly washed with water for 15-20 minutes, after which the acid-damaged surface should be washed with a 5% solution of baking soda, and the burnt with alkali - with a 3% solution of boric acid or an acetic solution. acids.

In case of contact with the mucous membrane of the eyes of acid or alkali, it is necessary to rinse the eyes thoroughly with a stream of water for 15-20 minutes, wash them with a 2% solution of baking soda, and burnt alkali with a 3% solution of boric acid or a 3% solution of acetic acid. acids.

In case of burns of the oral cavity with alkali, it is necessary to rinse with a 3% solution of acetic acid or a 3% solution of boric acid, for acid burns - with a 5% solution of baking soda.

If acid enters the respiratory tract, it is necessary to breathe with a 10% solution of baking soda sprayed with a spray bottle, if alkali enters, a sprayed 3% solution of acetic acid.

5.4.5. First aid for thermal burns.

In case of burns with fire, steam, hot objects, in no case should you open the formed blisters and bandage the burns with a bandage.

For first-degree burns (redness), the burned area is treated with cotton wool soaked in ethyl alcohol.

For second-degree burns (blisters), the burned area is treated with alcohol or a 3% manganese solution.

For third-degree burns (destruction of skin tissue), the wound is covered with a sterile dressing and a doctor is called.

5.4.6. First aid for bleeding.

In order to stop bleeding, you must:

  • raise the injured limb up;
  • close the bleeding wound with a dressing (from a bag) folded into a ball, press it from above, without touching the wound itself, hold for 4-5 minutes. If the bleeding stops without removing the applied material, put another pad from another bag or a piece of cotton on top of it and bandage the wounded area (with some pressure);
  • in case of severe bleeding that cannot be stopped with a bandage, compression of the blood vessels that feed the wounded area is applied by bending the limb at the joints, as well as with fingers, a tourniquet or a clamp. In case of heavy bleeding, you should immediately call a doctor.

5.5. Follow the instructions of the head of work to eliminate the emergency.

 We recommend interesting articles Section Standard instructions for labor protection:

▪ Meat grinder. Standard instruction on labor protection

▪ Arc welding. Standard instruction on labor protection

▪ Container driver. Standard instruction on labor protection

See other articles Section Standard instructions for labor protection.

Read and write useful comments on this article.

<< Back

Latest news of science and technology, new electronics:

Artificial leather for touch emulation 15.04.2024

In a modern technology world where distance is becoming increasingly commonplace, maintaining connection and a sense of closeness is important. Recent developments in artificial skin by German scientists from Saarland University represent a new era in virtual interactions. German researchers from Saarland University have developed ultra-thin films that can transmit the sensation of touch over a distance. This cutting-edge technology provides new opportunities for virtual communication, especially for those who find themselves far from their loved ones. The ultra-thin films developed by the researchers, just 50 micrometers thick, can be integrated into textiles and worn like a second skin. These films act as sensors that recognize tactile signals from mom or dad, and as actuators that transmit these movements to the baby. Parents' touch to the fabric activates sensors that react to pressure and deform the ultra-thin film. This ... >>

Petgugu Global cat litter 15.04.2024

Taking care of pets can often be a challenge, especially when it comes to keeping your home clean. A new interesting solution from the Petgugu Global startup has been presented, which will make life easier for cat owners and help them keep their home perfectly clean and tidy. Startup Petgugu Global has unveiled a unique cat toilet that can automatically flush feces, keeping your home clean and fresh. This innovative device is equipped with various smart sensors that monitor your pet's toilet activity and activate to automatically clean after use. The device connects to the sewer system and ensures efficient waste removal without the need for intervention from the owner. Additionally, the toilet has a large flushable storage capacity, making it ideal for multi-cat households. The Petgugu cat litter bowl is designed for use with water-soluble litters and offers a range of additional ... >>

The attractiveness of caring men 14.04.2024

The stereotype that women prefer "bad boys" has long been widespread. However, recent research conducted by British scientists from Monash University offers a new perspective on this issue. They looked at how women responded to men's emotional responsibility and willingness to help others. The study's findings could change our understanding of what makes men attractive to women. A study conducted by scientists from Monash University leads to new findings about men's attractiveness to women. In the experiment, women were shown photographs of men with brief stories about their behavior in various situations, including their reaction to an encounter with a homeless person. Some of the men ignored the homeless man, while others helped him, such as buying him food. A study found that men who showed empathy and kindness were more attractive to women compared to men who showed empathy and kindness. ... >>

Random news from the Archive

Gaming OLED TVs from LG 07.09.2019

In recent years, gamers have become one of the most powerful engines of the electronics industry. So, for example, while the market for personal computers and laptops is regularly declining, their gaming options, on the contrary, fly like hot cakes. Not surprisingly, many manufacturers are now asking the question: "What else would be released specifically for gamers?".

While some are churning out gaming smartphones, the Korean company LG decided to show originality and introduced special gaming TVs. A line of OLED models (model 65/55E9 and model 77/65/55C9) received support for Nvidia G-Sync technology. That is, if you connect a personal computer with an Nvidia video card to such TVs, you will receive automatic synchronization of the refresh rate of the graphics accelerator and the screen.

The new game line includes models with a diagonal of 55 to 77 inches. All of them have a resolution of 4K and a maximum frame rate of 120 Hz, which is very pleasant for games. The lag for 1440p content is 6 milliseconds, and for 4K video - 13 milliseconds, which is the best among all TVs of the brand.

Other interesting news:

▪ desert crocodiles

▪ The collision of black holes

▪ ASUS ROG Strix LC II Liquid Cooling Systems

▪ Laser device that produces particles with negative mass

▪ Inforce 6309L Single Board PC

News feed of science and technology, new electronics

 

Interesting materials of the Free Technical Library:

▪ section of the site Riddles for adults and children. Article selection

▪ Article Finger of God. Popular expression

▪ article How did the units of measurement come about? Detailed answer

▪ article Accountant for accounting of fixed assets. Job description

▪ solar collector article. Solar water heating installation. Encyclopedia of radio electronics and electrical engineering

▪ article Second session with cards (several tricks). Focus Secret

Leave your comment on this article:

Name:


Email (optional):


A comment:





All languages ​​of this page

Home page | Library | Articles | Website map | Site Reviews

www.diagram.com.ua

www.diagram.com.ua
2000-2024