Instructions for labor protection during the operation of an electric single-girder overhead crane. Full document

Occupational Safety and Health

Occupational Safety and Health / Standard instructions for labor protection

Comments on the article Comments on the article

Safe Operation

1. General requirements for labor protection

1.1. Hoisting mechanisms must be maintained and operated in accordance with the "Rules for the Design and Safe Operation of Hoisting Cranes. (DNAOP 0.00-1.03-02). Kharkiv. "Fort". 2002-1.1.10-1.04) Kiev "Fort". 01

1.2. Persons not younger than 18 years of age, specially trained and certified in accordance with the above Rules and having a note about this in the knowledge test certificate, may be allowed to operate the crane and rigging work.

1.3. Repair and maintenance of the crane must be carried out by electrical personnel with a group of at least III.

1.4. The electric crane must be equipped with a limit switch for automatically stopping the lifting mechanism of the lifting device, which is installed so that after the lifting device stops when lifting without load, the gap between it and the stop is at least 50 mm.

When lifting a load, it is forbidden to bring the hook holder to the limit switch and use the latter for automatic stop.

1.5. An electric crane must be equipped with two brakes: electromagnetic and load-resistant. The braking safety factor of the electromagnetic brake must be at least 1,25, and the load-resistant 1.1.

1.6. The electric crane must be equipped with a load limiter and a lower hook stop.

1.7. Before putting into operation, after overhaul and periodically, but at least once a year, the insulation resistance of the electrical equipment of the crane must be measured with a megohmmeter for a voltage of 1 V. The insulation resistance must be at least 500 MΩ.

The electrical equipment of the crane, which has an insulation resistance of less than 0,5 MΩ, must be dried.

1.8. The crane must be subjected to a full technical examination.

1.8.1. Checking the technical condition and maintenance.

Lubricate the crane in accordance with the lubrication chart. Lubrication of the intermediate shaft, motor-regulator, is carried out by packing during manufacture and after working out the recommended time, lubrication of the latch is carried out by laying in the place of contact of the bend with the hole in the channel shelf. The units are lubricated after disassembly during maintenance.

During the operation of the crane, the following must be performed:

  • shift maintenance (EO);
  • periodic maintenance (TO-1 and TO-2).

1.8.1.3. Every shift maintenance is carried out by the person who is to perform the work with the crane.

1.8.1.4. For daily maintenance, you must:

  • make an external inspection of the crane;
  • check the fastening of bolted connections;
  • check the reliability of fastening of the motor-reducer on the intermediate shaft, drive trolley;
  • check the presence of seals on electrical devices;
  • Check for markings and warning labels.

1.8.1.5. TO-1 includes the following works:

  • checking the fastening of bolted joints of metal structures, gearboxes, bearing caps, electric motors, end stops;
  • checking the condition of the electric hoist, monitoring the condition of the hoist according to the factory instructions;
  • checking the condition of current-collecting and current-carrying devices, as well as the insulation of electrical wiring.

1.8.1.6. Periodicity TO-1:

  • new tap - after 100 hours,
  • after overhaul - after 80 hours.

1.8.1.7. TO-2 includes the following works:

  • provided by TO-1;
  • checking the condition of the key connections of mechanisms;
  • checking the condition of gear reducers of crane movement mechanisms;
  • checking the mechanical protection of electrical equipment devices;
  • drawing up a list of defects and a list of parts to be replaced and repaired.

1.9. Lifting mechanisms and load-handling devices must be provided with plates and tags indicating the inventory number, permissible load capacity and the date of the next survey.

1.10. Mechanisms and devices should be stored in dry rooms on racks, decks or on special hooks and be well lubricated.

1.11. Do not allow the cleaner to clean under the faucet while it is running.

1.12. Instructions on safety measures when working on this crane must be located at the workplace.

2. Labor protection requirements before starting work

2.1. Prior to the start of work, a safety briefing should be carried out.

2.2. Before starting the crane, check the presence of lubrication at all lubricated points, make sure that the push-button posts are connected correctly, and that magnetic starters are turned on and off reliably. When lubricating, the following requirements must be met:

  • fill the bearing cavities with grease, approximately 2/3 of the volume;
  • fill gearboxes with grease to 1/3 of the volume.

2.3. It is necessary to provide free movement for the person operating the crane.

3. Labor protection requirements during work

3.1. When operating the crane, the following requirements must be observed:

  • Rules for the design and safe operation of cranes;
  • Rules for the installation of electrical installations.

3.2. It is impossible to work on a crane that is faulty and does not have the necessary guards. Do not repair yourself.

3.3. Secure cargo.

3.4. The mass and dimensions of the cargo must correspond to the passport data of the crane.

3.5. The place of work on lifting and moving goods must be well lit during work. In case of insufficient lighting of the place of work, heavy snowfall, fog, and also in other cases when the person serving the hoist poorly distinguishes the signals of the slinger or the load being moved, the work of the hoist must be stopped.

3.6. The supply of electrical voltage to the hoisting mechanism from an external power supply must be carried out using an input device with manual or remote control to relieve voltage.

3.7. Load hooks for loads over 3t. must be made rotating on closed ball bearings, with the exception of hooks for special purposes. Load hooks, from the mouth of which during operation it is possible for removable load-lifting devices to fall out, must be equipped with a safety lock.

3.8. Lifting a load for which slinging schemes have not been developed must be carried out in the presence and under the guidance of an employee responsible for the safe operation of cranes.

3.9. Loads suspended from the hook of the lifting mechanism must be securely tied with ropes so that during their movement the fall of individual parts (boards, woods, pipes, etc.) is excluded and the stable position of the load is ensured during movement. Slinging of long loads must be carried out with a double sling, and in the case of vertical lifting - with a sling with a safety clip.

3.10. In the cargo movement area, all openings must be closed or fenced and safety warning signs posted.

3.11. The load, when moving in a horizontal direction, must first be raised 0.5 m or more above the objects encountered on the way.

It is allowed to lower loads to a previously prepared place where their fall is excluded. For the convenience of extracting the slings at the place of its stop, it is necessary to lay strong gaskets.

3.12. It is forbidden to lower loads onto ceilings, supports and platforms without preliminary calculation of the strength of structures and overload them in excess of permissible loads.

3.13. It is forbidden to leave the load suspended, as well as to lift and move people with lifting mechanisms that are not designed for lifting them. In the event of a malfunction of the mechanism: when it is impossible to lower the load, the place under the suspended load must be fenced and posters "Danger zone", "Closed" should be posted.

3.14. Work with disabled or defective safety devices and brakes is prohibited. It is forbidden to simultaneously raise or lower two loads that are in close proximity.

3.15. Before lifting, the load must be raised to a height of no more than 300 m to check the correct slinging, the uniform tension of the slings, the stability of the lifting mechanism and the reliability of the brakes, only after that the load should be lifted to the required height. To correct the slinging, the load must be lowered.

3.16. The lifting of the load must be carried out smoothly, without jerking and swinging, avoiding its touching and twisting of the lines.

3.17. The deviation of the cargo rope from the vertical when lifting loads is allowed no more than 5 degrees. All friction parts of the hoists must be lubricated at least once a month.

3.18. When operating the crane, it is prohibited:

  • hauling a load with a hook or hauling a lifted load
  • lift a load, the weight of which exceeds the lifting capacity of the crane;
  • to quickly switch mechanisms from forward to reverse;
  • drag the load across the floor;
  • be under a lifted load.

3.19. To ensure trouble-free operation of the crane, it is necessary:

  • operate the crane in the specified passport mode of operation;
  • inspect and lubricate the crane in a timely manner;
  • control the tightening of bolted connections of the bogie cheeks, braces with ties, clamps;
  • control the gap between the guide rollers of the end beams.

It is forbidden to operate the crane if there is a gap between the guide rollers of more than 20 mm. With a large gap between the rollers, the ring gear of the rollers and the cheeks of the carts touch the lower shelf of the I-beam of the crane runway, which leads to jamming of the crane;

  • monitor the operation of parts that are most subject to wear (rollers, rollers, gears, wheels, I-beams);
  • stop work if defects are found in the operation of mechanisms;
  • properly suspend the load (it should not sway or touch the equipment).

3.20. Each employee, if he himself cannot take measures to eliminate the violation of the Rules and safety instructions, is obliged to immediately inform the administration of all violations of the rules and instructions he has noticed, as well as malfunctions of machines, mechanisms, devices and tools that pose a danger to people. used at work.

4. Labor protection requirements at the end of work

4.1. After finishing work, turn off all the electric motors of the mechanisms, put the workplace in order.

4.2. Remove all fixtures, slings, auxiliary ropes, put in order the rest of the inventory, tools.

4.3. Report the completion of work to the supervisor.

4.4. At the end of the work, report the noticed defects, as well as the measures taken to eliminate them, to the responsible person.

4.5. Tidy up overalls, clean from dust and dirt, take a shower.

5. Labor protection requirements in emergency situations

5.1 If a malfunction of equipment, tools, fixtures, equipment is detected, stop work and take measures to eliminate it. In case of impossibility or danger of eliminating the emergency on your own, inform the responsible person.

5.2. When repairing the crane and starting devices, a poster must be posted on the starting device: "Do not turn on - repair."

5.3. In case of deviations from the normal operation of the crane, immediately stop the crane and inform the responsible person.

5.4. In case of electric shock, it is necessary to immediately release the victim from the action of the current, observing the requirements of electrical safety, provide first aid and call a medical officer, notify the management.

5.5. In the event of a fire, inform the fire brigade by phone _______, management and start extinguishing.

5.6. In case of illness, injury, provide first aid to inform the medical institution and the master.

 We recommend interesting articles Section Standard instructions for labor protection:

▪ Working with abrasive and elbor tools. Standard instruction on labor protection

▪ Elevator dispatch operator. Standard instruction on labor protection

▪ High voltage testing of dielectric gloves. Standard instruction on labor protection

See other articles Section Standard instructions for labor protection.

Read and write useful comments on this article.

<< Back

Latest news of science and technology, new electronics:

Artificial leather for touch emulation 15.04.2024

In a modern technology world where distance is becoming increasingly commonplace, maintaining connection and a sense of closeness is important. Recent developments in artificial skin by German scientists from Saarland University represent a new era in virtual interactions. German researchers from Saarland University have developed ultra-thin films that can transmit the sensation of touch over a distance. This cutting-edge technology provides new opportunities for virtual communication, especially for those who find themselves far from their loved ones. The ultra-thin films developed by the researchers, just 50 micrometers thick, can be integrated into textiles and worn like a second skin. These films act as sensors that recognize tactile signals from mom or dad, and as actuators that transmit these movements to the baby. Parents' touch to the fabric activates sensors that react to pressure and deform the ultra-thin film. This ... >>

Petgugu Global cat litter 15.04.2024

Taking care of pets can often be a challenge, especially when it comes to keeping your home clean. A new interesting solution from the Petgugu Global startup has been presented, which will make life easier for cat owners and help them keep their home perfectly clean and tidy. Startup Petgugu Global has unveiled a unique cat toilet that can automatically flush feces, keeping your home clean and fresh. This innovative device is equipped with various smart sensors that monitor your pet's toilet activity and activate to automatically clean after use. The device connects to the sewer system and ensures efficient waste removal without the need for intervention from the owner. Additionally, the toilet has a large flushable storage capacity, making it ideal for multi-cat households. The Petgugu cat litter bowl is designed for use with water-soluble litters and offers a range of additional ... >>

The attractiveness of caring men 14.04.2024

The stereotype that women prefer "bad boys" has long been widespread. However, recent research conducted by British scientists from Monash University offers a new perspective on this issue. They looked at how women responded to men's emotional responsibility and willingness to help others. The study's findings could change our understanding of what makes men attractive to women. A study conducted by scientists from Monash University leads to new findings about men's attractiveness to women. In the experiment, women were shown photographs of men with brief stories about their behavior in various situations, including their reaction to an encounter with a homeless person. Some of the men ignored the homeless man, while others helped him, such as buying him food. A study found that men who showed empathy and kindness were more attractive to women compared to men who showed empathy and kindness. ... >>

Random news from the Archive

Team Group TM4PS4 and TM8PS4 SSDs 04.04.2015

Team Group introduced the TM4PS4 and TM8PS4 solid state drives, made in the form factor M.2 SSD (Next Generation Form Factor, NGFF).

Products are suitable for use both in mobile computers and in desktop systems, the motherboards of which are endowed with the appropriate slot. The SATA 3.0 interface is used with a bandwidth of up to 6 Gb / s.

The TM4PS4 measures 42,0 x 22,0 x 3,5mm and weighs 4g. The TM8PS4 measures 80,0 x 22,0 x 3,5mm and 9g. Both have a capacity of 128 or 256 GB.

TM4PS4 drives provide read and write speeds of up to 550 and 150 MB/s, respectively. The IOPS (input / output operations per second) for random reading in blocks of 4 KB reaches 70 thousand, for writing - 40 thousand.

TM8PS4 solutions deliver read/write speeds up to 560/300 MB/s. The IOPS value is up to 73K read and up to 70K write.

The claimed mean time between failures (MTBF) reaches 1,5 million hours. Supports TRIM commands and DevSleep mode, which extends the battery life of the mobile device. The products come with a three-year warranty.

Other interesting news:

▪ Rose genome deciphered

▪ Blue Origin space tourism ship

▪ Google will only use renewable energy

▪ The smallest microbe

▪ Radio beacons track Android and iOS devices

News feed of science and technology, new electronics

 

Interesting materials of the Free Technical Library:

▪ section of the site Normative documentation on labor protection. Article selection

▪ article The hydrostat controls the dive. Tips for a modeler

▪ article Can animals be guided by the mind? Detailed answer

▪ article Miscellaneous node. Travel Tips

▪ article A little about the GPA. Encyclopedia of radio electronics and electrical engineering

▪ article Soap bubble flies. physical experiment

Leave your comment on this article:

Name:


Email (optional):


A comment:





All languages ​​of this page

Home page | Library | Articles | Website map | Site Reviews

www.diagram.com.ua

www.diagram.com.ua
2000-2024