Menu English Ukrainian russian Home

Free technical library for hobbyists and professionals Free technical library


ENCYCLOPEDIA OF RADIO ELECTRONICS AND ELECTRICAL ENGINEERING
Free library / Encyclopedia of radio electronics and electrical engineering / Electrician

Section 1 General Rules

Norms of acceptance tests. Synchronous generators and compensators

Free technical library

Encyclopedia of radio electronics and electrical engineering / Rules for the installation of electrical installations (PUE)

Comments on the article Comments on the article

1.8.13. Synchronous generators with a power of more than 1 MW and a voltage above 1 kV, as well as synchronous compensators, must be tested in full in accordance with this paragraph.

Generators with a power of up to 1 MW and a voltage above 1 kV must be tested according to paragraphs 1-5, 7-15 of this paragraph.

Generators with voltage up to 1 kV, regardless of their power, must be tested according to paragraphs 2, 4, 5, 8, 10-14 of this paragraph.

1. Determination of the possibility of switching on without drying generators above 1 kV.

Should be produced in accordance with the manufacturer's instructions.

2. Measurement of insulation resistance.

The insulation resistance must not be less than the values ​​given in Table 1.8.1.

3. Testing the insulation of the stator winding with increased rectified voltage and measuring the leakage current by phase.

Each phase or branch is tested separately with other phases or branches connected to the housing. For generators with water-cooled stator windings, testing is carried out if this possibility is provided for in the design of the generator.

The test voltage values ​​are given in Table 1.8.2.

For turbine generators of the TGV-300 type, the test should be carried out along the branches.

The rectified test voltage for generators of the TGV-200 and TGV-300 types is 40 and 50 kV, respectively.

For turbogenerators TVM-500 (Unom=36,75 kV), the test voltage is 75 kV.

Measurement of leakage currents to construct curves of their dependence on voltage is carried out at no less than five values ​​of rectified voltage - from 0,2Umax to Umax in equal steps. At each stage the voltage is maintained for 1 minute. In this case, leakage currents are recorded after 15 and 60 s.

The obtained characteristics are assessed in accordance with the manufacturer's instructions.

4. Insulation test with increased voltage of industrial frequency.

The test is carried out according to the standards given in Table 1.8.3.

Each phase or branch is tested separately with other phases or branches connected to the housing.

The duration of application of the normalized test voltage is 1 min.

When conducting insulation tests with increased power frequency voltage, the following should be followed:

a) it is recommended to test the insulation of the generator stator windings before inserting the rotor into the stator. If the joining and assembly of the hydrogen generator stator is carried out at the installation site and subsequently the stator is installed in the shaft in assembled form, then its insulation is tested twice: after assembly at the installation site and after installing the stator in the shaft before the rotor is inserted into the stator.

During the test, the condition of the frontal parts of the machine is monitored: for turbogenerators - with the end shields removed, for hydrogenerators - with the ventilation hatches open;

b) testing the insulation of the stator winding for machines with water cooling should be carried out with the circulation of distilled water in the cooling system with a resistivity of at least 100 kOhm/cm and a nominal flow rate;

c) after testing the stator winding with increased voltage for 1 minute, for generators of 10 kV and above, reduce the test voltage to the rated voltage of the generator and maintain for 5 minutes to observe the corona of the frontal parts of the stator windings. In this case, there should be no yellow or red glow concentrated in individual points, the appearance of smoke, smoldering of bandages and similar phenomena. Blue and white glow is allowed;

d) testing of the insulation of the rotor winding of turbogenerators is carried out at the rated rotor speed;

e) before putting the generator into operation after completion of installation (for turbogenerators - after inserting the rotor into the stator and installing the end shields), it is necessary to carry out a control test with a rated power frequency voltage or a rectified voltage equal to 1,5 Un. Test duration 1 min.

5. DC resistance measurement.

The norms for permissible deviations of DC resistance are given in Table 1.8.4.

When comparing resistance values, they must be brought to the same temperature.

6. Measurement of the resistance of the rotor winding to alternating current.

The measurement is carried out in order to identify turn short circuits in the rotor windings, as well as the condition of the rotor damper system. For non-salient-pole rotors, the resistance of the entire winding is measured, and for salient-pole rotors, the resistance of each winding pole individually or two poles together. The measurement should be made with an input voltage of 3 V per turn, but not more than 200 V. When choosing the value of the input voltage, the dependence of the resistance on the value of the input voltage should be taken into account. The resistance of the windings of non-salient-pole rotors is determined at three to four speed levels, including the nominal one, and in a stationary state, maintaining the applied voltage or current constant. Resistance across poles or pairs of poles is measured only with a stationary rotor. Deviations of the obtained results from the manufacturer's data or from the average value of the measured pole resistances by more than 3-5% indicate the presence of defects in the rotor winding. The occurrence of turn faults is indicated by the abrupt nature of the decrease in resistance with increasing rotation speed, and poor quality in the contacts of the rotor damper system is indicated by the smooth nature of the decrease in resistance with increasing rotation speed. The final conclusion about the presence and number of closed turns should be made based on the results of taking the short circuit characteristics and comparing it with the manufacturer’s data.

7. Checking and testing of electrical equipment of excitation systems.

Standards for testing power equipment of thyristor self-excitation systems (hereinafter referred to as STS), independent thyristor excitation systems (STN), brushless excitation systems (BSV), and semiconductor high-frequency excitation (HF) systems are given. Checking the automatic excitation regulator, protection devices, control devices, automation, etc. is carried out in accordance with the manufacturer’s instructions.

Checking and testing of electric machine exciters should be carried out in accordance with 1.8.14.

7.1. Measurement of insulation resistance.

The insulation resistance values ​​at temperatures of 10-30 ºС must correspond to those given in Table 1.8.5.

7.2. Power frequency high voltage test.

The value of the test voltage is taken according to Table 1.8.5, the duration of application of the test voltage is 1 min.

7.3. Measurement of direct current resistance of windings of transformers and electrical machines in excitation systems.

The resistance of the windings of electrical machines (auxiliary generator in the STN system, inductor generator in the HF system, inverted synchronous generator in the BSV system) should not differ by more than 2% from the factory data; transformer windings (rectifiers in STS, STN, BSV systems; serial in individual STS systems) - by more than 5%. The resistances of the parallel branches of the working windings of inductor generators should not differ from each other by more than 15%, the phase resistances of the rotating exciters - by no more than 10%.

7.4. Checking transformers (rectifier, series, auxiliary needs, initial excitation, voltage and current instrument transformers).

The check is carried out in accordance with the standards given in 1.8.16, 1.8.17, 1.8.18. For series DC transformers, the relationship between the voltage on the open secondary windings and the generator stator current U2p.t.=f(Ist.) is also determined.

Characteristic U2p.t.=f(Ist.) is determined by taking the characteristics of a three-phase short circuit of the generator (unit) to Ist.nom. The characteristics of individual phases (with single-phase series transformers) should not differ from each other by more than 5%.

7.5. Determination of characteristics of an auxiliary synchronous power frequency generator in STN systems.

The auxiliary generator (AG) is checked in accordance with clause 8 of this paragraph. The short circuit characteristic of the high voltage generator is determined up to Ist.nom., and the idle speed characteristic is determined up to 1,3Ust.nom. with checking the turn insulation for 5 minutes.

7.6. Determination of the characteristics of an inductor generator together with a rectifier installation in an HF excitation system.

Produced with the series excitation winding turned off.

Characteristics of the no-load speed of an inductor generator together with a rectifier unit (RU), [Ust, Uv=f(In.v.), where In.v. - current in the independent excitation winding], determined to the value Uву, corresponding to twice the rated value of the rotor voltage, should not differ from the factory value by more than 5%. The voltage spread between series-connected AC valves should not exceed 10% of the average value.

The short circuit characteristics of the inductor generator together with the control device should also not differ from the factory value by more than 5%. With a rectified current corresponding to the rated rotor current, the spread of currents along the parallel branches in the arms of the control unit should not exceed ±20% of the average value. The load characteristic is also determined when working on the rotor up to Iрхх[Iр=f(Iв.в.)], where Iв.в. - exciter excitation current.

7.7. Determination of the external characteristics of a rotating subexciter in HF excitation systems.

When the load on the exciter changes (the load is an automatic excitation regulator), the change in the exciter voltage should not exceed the value specified in the factory documentation. The voltage difference between phases should not exceed 10%.

7.8. Checking the elements of an inverted synchronous generator and a rotating converter in the BSV system.

The DC resistance of the transition contact connections of the rotating rectifier is measured: the resistance of the current conductor, consisting of winding terminals and feed-through pins connecting the armature winding to the fuses (if any); connections of valves with fuses; the resistance of the rotating converter fuses themselves. The measurement results are compared with factory standards.

The tightening forces of valves, fuses of RC circuits, varistors, etc. are checked. in accordance with factory standards.

The reverse currents of the rotating converter valves are measured in a complete circuit with RC circuits (or varistors) at a voltage equal to the repeating voltage for a given class. Currents must not exceed the values ​​specified in the factory instructions for the excitation systems.

7.9. Determination of the characteristics of an inverted generator and a rotating rectifier in three-phase short circuit modes of the generator (unit).

The stator current Ist, exciter excitation current Iv.v., rotor voltage Uр are measured, and the compliance of the exciter characteristics Uр=f(In.v.) with the factory ones is determined. Based on the measured stator currents and the factory short circuit characteristic of the generator Ist=f(Iр), the correct settings of the rotor current sensors are determined. The deviation of the rotor current measured using a DTR-P type sensor (BSV output current) should not exceed 10% of the calculated value of the rotor current.

7.10. Testing of thyristor converters of STS, STN, BSV systems.

Insulation resistance measurement and high voltage testing are carried out in accordance with Table 1.8.5.

Hydraulic tests are carried out with increased water pressure on thyristor converters (TC) with a water cooling system. The pressure value and the time of its exposure must comply with the manufacturer’s standards for each type of converter. The TC insulation is rechecked after filling with distillate (see Table 1.8.3).

The absence of broken thyristors or damaged RC circuits is checked. The test is performed using an ohmmeter.

The integrity of the parallel circuits of the fuse link of each power fuse is checked by measuring the DC resistance.

The state of the thyristor control system and the range of regulation of the rectified voltage when exposed to the thyristor control system are checked.

The TP is checked when the generator is operating in nominal mode with the rated rotor current. The check is carried out to the following extent:

  • distribution of currents between parallel branches of the converter arms; the deviation of the current values ​​in the branches from the arithmetic mean value of the branch current should be no more than 10%;
  • distribution of reverse voltages between series-connected thyristors, taking into account switching overvoltages; the deviation of the instantaneous value of the reverse voltage from the average value on the branch thyristor should be no more than ±20%;
  • current distribution between parallel-connected converters; currents should not differ by more than ±10% from the average calculated value of the current through the converter;
  • current distribution in the branches of the same-named arms of parallel-connected transformer transformers; the deviation from the average calculated value of the current of a branch of the same arms should not be more than ±20%.

7.11. Checking the rectifier diode installation in the RF excitation system.

Performed when the generator is operating in nominal mode with the rated rotor current. When checking, it is determined:

  • current distribution between parallel branches of the arms; deviation from the average value should be no more than ±20%;
  • distribution of reverse voltages across valves connected in series; the deviation from the average value should be no more than ±20%.

7.12. Checking switching equipment, power resistors, auxiliary equipment for excitation systems.

The check is carried out in accordance with the instructions of the manufacturer and 1.8.34.

7.13. Measuring the temperature of power resistors, diodes, fuses, busbars and other elements of converters and cabinets in which they are located.

Measurements are performed after switching on the excitation systems under load. The temperatures of the elements should not exceed the values ​​​​specified in the manufacturers' instructions. When checking, it is recommended to use thermal imagers; the use of pyrometers is allowed.

8. Definition of generator characteristics:

a) three-phase short circuit. The characteristic is removed when the stator current changes to the rated one. Deviations from the factory specifications must be within the measurement error.

A decrease in the measured characteristic, which exceeds the measurement error, indicates the presence of turn short circuits in the rotor winding.

For generators operating in a block with a transformer, the short-circuit characteristic of the entire block is removed (with the installation of a short circuit behind the transformer). The characteristics of the generator itself, operating in a block with a transformer, may not be determined if there are corresponding test reports at the manufacturer’s bench.

For synchronous compensators without an accelerating motor, the characteristics of a three-phase short-circuit are measured during the freewheel if there is no characteristic taken at the factory;

b) idling. Raising the voltage of the rated frequency at idle to 130% of the rated voltage of turbogenerators and synchronous compensators, up to 150% of the rated voltage of hydraulic generators. It is allowed to take the idle characteristics of a turbo and hydrogenerator up to the rated excitation current at a reduced generator speed, provided that the voltage on the stator winding does not exceed 1,3 rated. For synchronous compensators, it is allowed to take the run-down characteristic. For generators operating in a block with transformers, the idle characteristic of the block is removed; in this case, the generator is excited to 1,15 rated voltage (limited by the transformer). The idle speed characteristic of the generator itself, disconnected from the unit’s transformer, may not be taken if there are corresponding test reports from the manufacturer. The deviation of the idle speed characteristics from the factory one is not standardized, but must be within the measurement error.

9. Test of interturn insulation.

The test should be carried out by raising the voltage of the rated frequency of the generator at idle to a value corresponding to 150% of the rated stator voltage of hydraulic generators, 130% of turbogenerators and synchronous compensators. For generators operating in a block with a transformer, see instructions in paragraph 9. In this case, you should check the symmetry of the voltages across phases. The duration of the test at the highest voltage is 5 minutes.

It is recommended to test the interturn insulation simultaneously with taking the idle speed characteristics.

10. Vibration measurement.

Vibration (range of vibration displacements, double amplitude of vibrations) of generator components and their electric machine exciters should not exceed the values ​​​​given in Table 1.8.6.

Vibration of bearings of synchronous compensators with a nominal rotor speed of 750-1500 rpm should not exceed 80 μm in the range of vibration displacements or 2,2 mm s-1 in the root mean square value of the vibration speed.

11. Checking and testing the cooling system.

Produced in accordance with the manufacturer's instructions.

12. Checking and testing the oil supply system.

Produced in accordance with the manufacturer's instructions.

13. Checking the insulation of the bearing during the operation of the generator (compensator).

It is made by measuring the voltage between the ends of the shaft, as well as between the foundation plate and the insulated bearing housing. In this case, the tension between the foundation plate and the bearing should be no more than the tension between the ends of the shaft. A difference between voltages of more than 10% indicates an insulation failure.

14. Testing the generator (compensator) under load.

The load is determined by practical capabilities during the acceptance tests. The heating of the stator at a given load must correspond to the specifications.

15. Determination of the characteristics of the collector exciter.

The no-load characteristic is determined up to the highest (ceiling) voltage value or the value set by the manufacturer.

The load characteristic is taken when the load on the generator rotor is not lower than the rated excitation current of the generator. Deviations of characteristics from the factory ones must be within the permissible measurement error.

16. Testing the terminal leads of the stator winding of the TGV series turbogenerator.

In addition to the tests specified in Tables 1.8.1 and 1.8.3, end terminals with capacitor glass epoxy insulation are subjected to tests according to clauses 16.1 and 16.2.

16.1. Measurement of the dielectric loss tangent (tg δ).

The measurement is carried out before installing the end terminal on the turbogenerator at a test voltage of 10 kV and an ambient temperature of 10-30ºС.

The tg δ value of the assembled terminal should not exceed 130% of the value obtained from factory measurements. In the case of measuring tg δ of the end terminal without porcelain covers, its value should not exceed 3%.

16.2. Checking gas tightness.

The gas tightness test of the end terminals, tested at the factory with a pressure of 0,6 MPa, is carried out with a compressed air pressure of 0,5 MPa.

The end terminal is considered to have passed the test if, at a pressure of 0,3 MPa, the pressure drop does not exceed 1 kPa/h.

17. Measurement of the residual voltage of the generator when the AGP is turned off in the rotor circuit.

The value of residual stress is not standardized.

18. Testing the generator (compensator) under load.

The load is determined by practical capabilities during the acceptance tests. Stator heating at a given load must correspond to the manufacturer's data.

Table 1.8.1. Acceptable values ​​of insulation resistance and adsorption coefficient

Test item Megaohmmeter voltage, V Permissible value of insulation resistance, MΩ Note
1. Stator winding 500, 1000, 2500 Not less than 10 MΩ per 1 kV of rated line voltage. For each phase or branch separately relative to the housing and other grounded phases or branches. R value60/R15 not less than 1,3
2500 According to the manufacturer's instructions. When distillate flows through the winding
2. Rotor winding 500, 1000 Not less than 0,5 (with water cooling - with drained winding) It is allowed to commission generators with a power not exceeding 300 MW with non-salient pole rotors, with indirect or direct air and hydrogen cooling of the winding, which has an insulation resistance of at least 2 kOhm at a temperature of 75 ºС or 20 kOhm at a temperature of 20 ºС. At higher power, putting the generator into operation with an insulation resistance of the rotor winding below 0,5 MOhm (at 10-30 ºС) is allowed only by agreement with the manufacturer.
1000 According to the manufacturer's instructions. When distillate flows through the cooling channels of the winding.
3. Excitation circuits of the generator and collector exciter with all connected equipment (without rotor winding and exciter) 500-1000 At least 1,0
4. Windings of collector exciter and subexciter 1000 At least 0,5
5. Bandages of the armature and collector of the collector exciter and subexciter 1000 At least 0,5 With grounded armature winding
6. Insulated stator steel tie bolts (measurable) 1000 At least 0,5
7. Bearings and shaft seals 1000 Not less than 0,3 for hydrogen generators and 1,0 for turbogenerators and compensators. For hydrogenerators, measurement is carried out if the design of the generator allows and more stringent standards are not specified in the factory instructions.
8. Diffusers, fan shields and other generator stator components 500, 1000 According to factory requirements
9. Thermal sensors with connecting wires, including connecting wires laid inside the generator
- with indirect cooling of stator windings 250 or 500 At least 1,0 Megaohmmeter voltage - according to the factory instructions
- with direct cooling of the stator windings 500 At least 0,5
10. Termination of the stator winding of the TGV series turbogenerators 2500 1000 The measurement is made before connecting the output to the stator winding

Table 1.8.2. Test rectified voltage for stator windings of synchronous generators and compensators

Generator power, MW, compensator, MB A Rated voltage, kV Amplitude test voltage, kV
Less than 1 All voltages 2,4UMr.+1,2
1 and more Until 3.3 2,4+1,2UMr.
St. 3,3 to 6,6 will include. 1,28x2,5UMr.
St. 6,6 to 20 will include. 1,28(2UMr.+ 3)
St. 20 to 24 will include. 1,28(2UMr.+ 1)

Table 1.8.3. Power frequency test voltage for windings of synchronous generators and compensators

Test item Characteristic or type of generator Test voltage, kV Note
1. Generator stator winding Power up to 1 MW, rated voltage above 0,1 kV 0,8(2UMr.+1) but not less than 1,2
Power from 1 MW and above, rated voltage up to 3,3 kV inclusive 0,8(2UMr.+ 1)
Power from 1 MW and above, rated voltage over 3,3 to 6,6 kV inclusive 0,8 2UMr.
Power from 1 MW and above, rated voltage over 6,6 to 20 kV inclusive 0,8(2UMr.+ 3)
Power from 1 MW and above, rated voltage over 20 kV 0,8(2UMr.+ 1)
2. The stator winding of a hydrogenerator, the fusion or joining of stator parts of which is carried out at the installation site, after complete assembly of the winding and insulation of connections. Power from 1 MW and above, rated voltage up to 3,3 kV inclusive 2UMr.+1 If the stator is assembled at the installation site, but not on the foundation, then before installing the stator on the foundation, it is tested according to paragraph 2, and after installation - according to paragraph 1 of the table
Power from 1 MW and above, rated voltage over 3,3 to 6,6 kV inclusive 2,5UMr.
Power from 1 MW and above, rated voltage over 6,6 kV 2UMr.+3
3. Winding of salient pole rotor Generators of all capacities 0,8 UMr. generator excitation, but not lower than 1,2 and not higher than 2,8 kV
4. Winding of a non-salient pole rotor Generators of all capacities 1,0 The test voltage is taken equal to 1 kV when this does not contradict the requirements of the manufacturer's technical specifications. If the technical specifications provide for more stringent test standards, the test voltage must be increased.
5. Winding of collector exciter and subexciter Generators of all capacities 0,8 UMr.generator excitation, but not lower than 1,2 and not higher than 2,8 kV Concerning the body and bandages
6. Excitation circuits Generators of all capacities 1,0
7. Excitation rheostat Generators of all capacities 1,0
8. Zero and AGP damping circuit resistor Generators of all capacities 2,0
9. Stator winding terminal TGV-200, TGV-200M, 31,0*, 34,5** Tests are carried out before installing the end leads on the turbogenerator

* For terminals tested at the factory together with the stator winding insulation.

** For reserve terminals before installation on the turbogenerator.

Table 1.8.4. Permissible deviation of DC resistance

Test object Normal value
Stator winding (measurement is carried out for each phase or branch separately) The measured resistances in a practically cold state of the windings of various phases should not differ from one another by more than 2%. Due to design features (long connecting arcs, etc.), the discrepancy between the resistances of the branches of some types of generators can reach 5%.
Rotor winding The measured winding resistance should not differ from the manufacturer's data by more than 2%. For salient pole rotors, measurements are made for each pole individually or in pairs.
Field quenching resistor, excitation rheostats The resistance should not differ from the manufacturer's data by more than 10%.
Collector exciter excitation windings The measured resistance value should not differ from the original data by more than 2%.
Exciter armature winding (between collector plates) The measured resistance values ​​should not differ from each other by more than 10%, except when this is due to the connection diagram.

Table 1.8.5. Insulation resistance and test voltages of excitation system elements

Test object Insulation resistance measurement Power frequency test voltage value Note
Megaohmmeter voltage, V Minimum value of insulation resistance, MΩ
1. Thyristor converter (TC) of the rotor circuit of the main generator in the excitation systems STS, STN: current-carrying circuits of the converters, protective circuits connected to the thyristors, secondary windings of the output transformers of the control system, etc.; disconnected disconnectors adjacent to the converters 2500 5 0,8 of the factory test voltage of the TP, but not less than 0,8 of the factory test voltage of the rotor winding Regarding the housing and the secondary circuits of the TP connected to it (primary windings of pulse transformers of the STS, block contacts of power fuses, secondary windings of current divider transformers, etc.), adjacent to the TP of the power elements of the circuit (secondary windings of transformers for auxiliary needs in the STS, other sides of disconnectors in STS of a number of modifications).
(STS), primary windings of auxiliary transformers (STS). In water-cooled TP systems there is no water during testing Thyristors (anodes, cathodes, control electrodes) must be short-circuited during testing, and the blocks of the SUT thyristor control system must be pulled out of the connectors
2. Thyristor converter in the excitation circuit of the exciter of the BSV system: current-carrying parts, thyristors and associated circuits (see paragraph 1). Thyristor converter in the excitation circuit of the VG system of the STN system 1000 5 0,8 of the factory test voltage of the TP, but not less than 0,8 of the test voltage of the excitation winding of the inverted generator or VG Regarding the housing and the secondary circuits of the TP connected to it, not connected to the power circuits (see clause 1). During testing, the TP is disconnected at the input and output from the power circuit; thyristors (anodes, cathodes, control electrodes) must be short-circuited, and the SUT blocks must be pulled out of the connectors
3. Rectifier installation in the RF excitation system. 1000 5 0,8 of the factory test voltage of the rectifier installation, but not less than 0,8 of the test voltage of the rotor winding. Regarding the body. During testing, the rectifier unit is disconnected from the power source and the rotor winding; the power bus and output bus (A, B, C, +, -) are combined.
4. Auxiliary synchronous generator VG in STN systems:
- stator windings 2500 5,0 0,8 factory test voltage of the VG stator winding, but not less than 0,8 test voltage of the main generator rotor winding Relative to the body and between the windings
- excitation windings 1000 5,0 0,8 factory test voltage of the excitation winding of the inverted generator or VG Relative to the body
5. Inductor generator in the RF excitation system:
- working windings (three phases) and series excitation winding 1000 5,0 0,8 factory test voltage of the windings, but not less than 0,8 test voltage of the generator rotor winding Relative to the housing and the independent excitation windings connected to it, between the windings
- independent excitation windings 1000 5,0 0,8 factory test voltage of the windings Relative to the case and between windings of independent excitation
6. Subexciter in the RF excitation system 1000 5,0 0,8 factory test voltage Each phase relative to others connected to the body
7. Inverted generator together with a rotating converter in the BSV system:
- armature windings together with a rotating converter; 1000 5,0 0,8 factory test voltage of the armature winding Regarding the body. The exciter is disconnected from the generator rotor; valves, RC circuits or varistors are bypassed (connected +, -, AC studs); raised brushes on measuring slip rings
- excitation windings of the inverted generator 500 5,0 0,8 factory test voltage of the excitation winding, but not less than 1,2 kV Regarding the hull. Excitation windings disconnected from the circuit
8. Rectifier transformer VT in STS systems. 2500 5,0 0,8 factory test voltage of the transformer windings; Relative to the body and between the windings
Rectifier transformers in excitation systems VG (STN) and BSV: secondary windings for VG and BSV - not less than 1,2 kV
- primary winding 2500 5,0
- secondary winding 1000
9. Series transformers in STS systems 2500 5,0 0,8 factory test voltage of the windings Relative to the body and between the windings
10. Current conductors connecting power supplies (VG in the STN system, VT and DC in the STS system), an inductor generator in the HF system with thyristor or diode converters, DC current conductors:
- without attached equipment; 2500 10 0,8 factory test voltage of conductors Relative to earth between phases.
- with attached equipment 2500 5,0 0,8 rotor winding factory test voltage Relative to earth between phases.
11. Power elements of STS, STN, HF systems (power supplies, converters, etc.) with all connected equipment up to excitation input switches or converter output disconnectors (circuits of excitation systems without backup exciters):
- systems without water cooling of converters and with water cooling with a cooling system not filled with water; 1000 1,0 1,0 kV Relative to the body
- with the TP cooling system filled with water (with a resistivity of at least 75 kOhm cm) 1000 0,15 1,0 kV Control units extended
12. Power excitation circuits of the generator without a rotor winding (after the excitation input switch or DC disconnectors (see paragraph 11); AGP device, arrester, power resistor, busbars, etc. Circuits connected to the measuring rings in the BSV system ( rotor winding is disconnected) 1000 0,1 0,8 rotor factory test voltage Regarding "ground"

Table 1.8.6. Limit values ​​of vibration of generators and their exciters

Controlled Node Vibration, µm, at rotor speed, rpm Note
to 100 from 100 to 187,5 from 187,5 to 375 from 375 to 750 1500 3000
1. Bearings for turbogenerators and exciters, crosspieces with built-in guide bearings for vertical hydraulic generators 180 150 100 70 50* 30* Vibration of bearings of turbogenerators, their exciters and horizontal hydraulic generators is measured on the top bearing cover in the vertical direction and at the connector in the axial and transverse directions. For vertical hydraulic generators, the vibration values ​​given refer to the horizontal and vertical directions.
2. Slip rings of the rotor of turbogenerators - - - - - 200 Vibrations are measured in horizontal and vertical directions.

* if vibration velocity monitoring equipment is available, it is measured; the root-mean-square value of vibration velocity should not exceed 2,8 mm s-1 along the vertical and transverse axes and 4,5 mm s-1 along the longitudinal axis.

See other articles Section Rules for the installation of electrical installations (PUE).

Read and write useful comments on this article.

<< Back

Latest news of science and technology, new electronics:

The world's tallest astronomical observatory opened 04.05.2024

Exploring space and its mysteries is a task that attracts the attention of astronomers from all over the world. In the fresh air of the high mountains, far from city light pollution, the stars and planets reveal their secrets with greater clarity. A new page is opening in the history of astronomy with the opening of the world's highest astronomical observatory - the Atacama Observatory of the University of Tokyo. The Atacama Observatory, located at an altitude of 5640 meters above sea level, opens up new opportunities for astronomers in the study of space. This site has become the highest location for a ground-based telescope, providing researchers with a unique tool for studying infrared waves in the Universe. Although the high altitude location provides clearer skies and less interference from the atmosphere, building an observatory on a high mountain poses enormous difficulties and challenges. However, despite the difficulties, the new observatory opens up broad research prospects for astronomers. ... >>

Controlling objects using air currents 04.05.2024

The development of robotics continues to open up new prospects for us in the field of automation and control of various objects. Recently, Finnish scientists presented an innovative approach to controlling humanoid robots using air currents. This method promises to revolutionize the way objects are manipulated and open new horizons in the field of robotics. The idea of ​​controlling objects using air currents is not new, but until recently, implementing such concepts remained a challenge. Finnish researchers have developed an innovative method that allows robots to manipulate objects using special air jets as "air fingers". The air flow control algorithm, developed by a team of specialists, is based on a thorough study of the movement of objects in the air flow. The air jet control system, carried out using special motors, allows you to direct objects without resorting to physical ... >>

Purebred dogs get sick no more often than purebred dogs 03.05.2024

Caring for the health of our pets is an important aspect of the life of every dog ​​owner. However, there is a common assumption that purebred dogs are more susceptible to diseases compared to mixed dogs. New research led by researchers at the Texas School of Veterinary Medicine and Biomedical Sciences brings new perspective to this question. A study conducted by the Dog Aging Project (DAP) of more than 27 companion dogs found that purebred and mixed dogs were generally equally likely to experience various diseases. Although some breeds may be more susceptible to certain diseases, the overall diagnosis rate is virtually the same between both groups. The Dog Aging Project's chief veterinarian, Dr. Keith Creevy, notes that there are several well-known diseases that are more common in certain breeds of dogs, which supports the notion that purebred dogs are more susceptible to disease. ... >>

Random news from the Archive

Chips based on 14nm technology 2 generations 20.01.2016

Samsung Electronics announced the start of mass production of chips using an optimized 14-nanometer LPP (Low-Power Plus) process. This is the second generation of 14nm FinFET manufacturing technology.

Back in the first quarter of 2015, the company announced the launch of production of the Exynos 7 Octa processor based on the innovative 14nm LPE (Low-Power Early) technology. As noted, the use of new technology has ensured high performance and energy efficiency of the new Exynos 8 Octa processor, as well as many other products developed by partners and produced using Samsung FinFET technology. Among them is the Qualcomm Snapdragon 820 processor from Qualcomm Technologies, which will be used in mobile devices in the first half of 2016.

By incorporating 14D FinFET into semiconductor devices, significant performance gains can be achieved while power consumption is reduced, Samsung says. The new 15nm LPP process delivers a 14% increase in processing speed and a XNUMX% reduction in power consumption compared to the previous XNUMXnm LPE process through improved transistor structure and process optimization. In addition, the use of fully depleted FinFET transistors provides additional manufacturing advantages and opens up great scalability.

Other interesting news:

▪ Reusable and erasable ink

▪ V-Phone X3 off-road smartphone with 4500 mAh battery

▪ A simple way to extract uranium from seawater

▪ Holes in the light tied in knots

▪ Rivian frost-resistant electric vehicles

News feed of science and technology, new electronics

 

Interesting materials of the Free Technical Library:

▪ site section And then an inventor (TRIZ) appeared. Article selection

▪ article Electric terminal from a tube. Tips for the home master

▪ article How is wax obtained? Detailed answer

▪ article Caterpillar motorized towing vehicle Seal. Personal transport

▪ article Celluloid varnishes (zaponlaks). Simple recipes and tips

▪ article How to guess the title of a book. Focus secret

Leave your comment on this article:

Name:


Email (optional):


A comment:





All languages ​​of this page

Home page | Library | Articles | Website map | Site Reviews

www.diagram.com.ua

www.diagram.com.ua
2000-2024