Safe Operation

1. General requirements for labor protection

1.1. To perform the work of an electrician for the repair and maintenance of electrical equipment of hoisting machines, persons are allowed at least 18 years of age who have passed a medical examination, trained according to the appropriate program and certified by the qualification commission, as well as received instructions on safe working methods directly at the workplace with registration in the Instruction Registration Log.

1.2. An electrician authorized to repair and maintain hoisting machines must have an electrical safety group of at least III.

1.3. A certified electrician is issued a certificate for the right to repair and maintain electrical equipment of hoisting machines signed by the chairman of the commission, sealed with a stamp.

1.4. The admission to the work of an electrician for the repair and maintenance of hoisting machines is issued by order of the enterprise (workshop, section) after the issuance of a certificate and instructions on labor protection.

1.5. Re-testing the knowledge of an electrician who repairs and maintains hoisting machines is carried out:

  • periodically, at least once every 12 months;
  • when moving from one enterprise to another;
  • at the request of the person responsible for the supervision of hoisting machines at the enterprise, or the inspector of Gosgortekhnadzor. Knowledge is tested in the scope of the instructions for labor protection, the relevant sections of the "Safety regulations for the operation of electrical installations of consumers" and "Rules for the design and safe operation of cranes".

1.6. An electrician admitted to independent work on the repair and maintenance of electrical equipment of hoisting machines must know:

  • labor protection instructions for electricians when servicing general production electrical equipment with voltage up to 1000 V;
  • basic provisions of general electrical engineering;
  • purpose, arrangement and principle of operation of units, mechanisms and electrical equipment of hoisting machines;
  • electrical circuits fixed for the maintenance of lifting machines;
  • the relevant sections of the "Safety regulations for the operation of electrical installations of consumers" and "Rules for the design and safe operation of cranes";
  • the main causes of damage and accidents on the electrical equipment of hoisting machines, be able to find and eliminate them.

1.7. The electrician is obliged to comply with the internal labor regulations of the enterprise.

Smoking in production and auxiliary premises and on the territory of the enterprise is allowed only in places specially designated for this purpose.

1.8. During work, the electrician may be exposed to the following hazardous and harmful production factors:

  • noise and vibration from working mechanisms;
  • electricity;
  • industrial microclimate.

1.9. The electrician must be provided with personal protective equipment:

  • cotton overalls;
  • dielectric gloves;
  • dielectric galoshes.

1.10. An electrician admitted to independent work on the repair and maintenance of electrical equipment of hoisting machines must:

  • to inspect and repair electrical equipment of hoisting machines;
  • prepare the electrical equipment of hoisting machines for technical certification.

1.11. An electrician for the repair and maintenance of lifting machines must know and observe the rules of personal hygiene.

1.12. An electrician for the repair and maintenance of hoisting machines must be able to provide the victim with first (pre-medical) aid in case of an accident.

1.13. If any questions arise during the work related to its safe performance, it is necessary to contact the person responsible for the safe performance of work.

1.14. A trained and certified electrician for the repair and maintenance of electrical equipment of lifting machines is fully responsible for violation of the requirements of this Instruction in accordance with applicable law.

2. Safety requirements before starting work

2.1. Before starting work, the electrician must familiarize himself with the entries in the operational log, accept from the electrician who handed over the shift the technical documentation approved by the power engineer, safety protective equipment, make an entry on the acceptance of the shift in the operational log and sign.

2.2. Make sure the work area is adequately lit.

2.3. Tidy up the workplace, remove all items that may interfere with safe work.

2.4. Put on the appropriate overalls, prepare serviceable and tested personal protective equipment (dielectric gloves, galoshes).

2.5. Notify the foreman or supervisor of all noticed shortcomings in the workplace and do not start work until their instructions.

3. Safety requirements before starting work

During maintenance between overhauls

3.1. Work carried out to eliminate faults in the electrical equipment of hoisting machines at the request of machinists and non-electrical personnel, and inspections regarding the safety of their implementation are divided into:

  • for work performed in the order of current operation, with an entry in the operational log;
  • work performed by order of administrative and technical personnel with an electrical safety group of at least IV, with an entry in the operational log.

In the order of current operation, the electrician on duty for servicing the electrical equipment of hoisting machines is allowed, in the presence of a driver (crane operator) who has an electrical safety group II, to perform the following work:

  • inspection of electrical equipment;
  • replacement of burnt-out lamps and fuse-links;
  • repair and replacement of electric devices located in the cab of the driver (crane operator);
  • checking the correct operation of safety instruments and devices, lighting, signaling and blocking, with the exception of signaling devices indicating the presence of voltage on the main trolleys.

3.2. The electrician, having received an application from the driver (crane operator), must make an entry in the operational log, indicating the date and time of receipt of the application, the name and position of the person who submitted the application, the content of the application and the start time of work.

After eliminating the detected faults in the same journal, it is necessary to make a record of the content of the work performed and the time of their completion.

At the same time, a record is made of troubleshooting in the logbook of the driver (crane operator).

3.3. If faults are found that are not related to the list of works performed in the order of current operation, the electrician on duty must report to the shift supervisor about the deficiencies found.

3.4. Work performed by order, with an entry in the operational log:

  • replacement of burned-out electric motors;
  • replacement of electromagnetic coils and brakes;
  • adjustment of limit switches;
  • conducting periodic inspections.

3.5. The execution of work according to the order must be carried out by two persons with an electrical safety group of at least III, with complete removal of voltage, with the implementation of the necessary organizational and technical measures in accordance with the requirements of the "Safety Rules for the Operation of Consumer Electrical Installations" with an entry in the operational log.

3.6. The person giving the order must determine the composition of the team, the foreman and organize the admission of the team to work.

3.7. For all types of repairs and inspections of the electrical equipment of a crane located between two operating cranes, a work permit must be issued with entries in the watch logs of all cranes of this span.

3.8. Periodic inspection of the electrical equipment of hoisting machines is aimed at identifying and eliminating possible malfunctions in electrical equipment, safety devices and devices, in power circuits, control circuits, alarm circuits, checking the serviceability of safety protective equipment and fire extinguishing equipment and confirming in the journal of periodic inspections that the electrical equipment of hoisting machines is in good condition.

3.9. When inspecting the electrical equipment of cranes, the adjustment and switching on of the mechanisms must be carried out at the signal of the person performing the inspection.

3.10. When moving the crane bridge, persons inspecting and troubleshooting the crane's electrical equipment should be in the cab or on the bridge deck, while avoiding touching the protruding parts of the ceiling, columns, fittings.

3.11. When you reach the deck of the crane gallery, the switch in the driver's cab must be turned off and a poster is posted on its drive: "Do not turn it on! People are working." Remove the poster - only by order of operational personnel.

3.12. When inspecting and troubleshooting the electrical equipment of the crane, all precautions must be observed, the necessary serviceable and tested protective equipment must be used.

3.13. Upon completion of the repair and inspection, all removed guards on electrical equipment and on electrical appliances must be put in place and strengthened.

3.14. The results of the inspection for each crane separately must be recorded in the journal of periodic inspections indicating the date, time of the inspection, a summary of the identified and eliminated deficiencies, and there must be a signature of the person performing the repair.

3.15. When troubleshooting, adjusting and inspecting the electrical equipment of the crane, it is prohibited:

  • enter the crane and leave it during its movement;
  • go out onto the crane tracks, walk along the crane tracks, climb from one crane to another;
  • to adjust the brake of the mechanism with a raised load, as well as to install devices for releasing the brake manually;
  • leave tools, as well as loose equipment and parts on the gallery floor or on the trolley;
  • dump tools, materials and spare parts from the crane.

3.16. For portable power tools and portable lamps, use a safe voltage not higher than 36 V.

3.17. When performing all work, the electrician must withdraw the key-brand from the crane operator in the manner established at the enterprise for the use of the key-brand system.

During scheduled repairs

3.18. The withdrawal of the crane for repair should be carried out by the person responsible for maintaining the lifting machines in good condition, in accordance with the scheduled repair schedule with the issuance of an order for work in electrical installations.

The outfit is issued by persons of the electrical personnel of the site, authorized by the order of the chief power engineer of the enterprise.

The lines of the order "Separate Instructions" fix additional safety measures related to working at height, to prevent running cranes from colliding with the one being repaired, access of repair personnel to the crane tracks of existing cranes, etc. The completed work order is handed over to the person responsible for maintaining the hoisting machines in good condition the day before the start of the repair, who authorizes work in the "Separate Instructions" lines of the work order with his signature and returns it to the person who issued the work order.

The person responsible for maintaining the hoisting machines in good condition, before the start of the repair, is obliged to make the following entry in the watch log of the driver (crane operator) of the crane being repaired: "I authorize the work foreman comrade ______________ to repair the electrical equipment of the crane No. ___ by _______ type of repair from ___ h ____ min ____ day _____ month _______ year ____ to ____ h _____ min _____ day _____ month _____ year" and sign.

3.19. The order for work in electrical devices must indicate the composition of the team, the foreman who allows work, the person issuing the order; necessary technical measures to ensure the safety of work during the repair of electrical equipment of the crane; date and time of commencement of work, admission of the brigade and completion of work.

3.20. The admission of the brigade to the repair of the electrical equipment of the crane is made by the person of the operating personnel on the basis of an order for work in electrical installations and the permission of the person responsible for maintaining the lifting machines in good condition. The admitting person makes an entry in the operational log of the power engineering service with the design of the appropriate columns in the order and admits the brigade to the crane.

3.21. To ensure safety during the repair of the electrical equipment of the crane, it is necessary to put it on the repair site, make the necessary shutdowns, close the knife switch drive with a lock, hang safety warning posters, install portable grounding and make a fence under the repair site.

3.22. Repair of the electrical equipment of the crane can be carried out by electricians who have a certificate for the right to repair and maintain hoisting machines, at least two people with an electrical safety group of at least III.

3.23. Keep unauthorized persons away from the crane. It is forbidden to enter the crane tracks without obtaining a special permit.

3.24. Upon completion of the repair and closing of the order, the person responsible for maintaining the hoisting machines in good condition checks the readiness of the crane for operation, makes an entry in the crane logbook: "I allow the crane to operate from ___ h ____ min ____ day ____ month ____ year" with his signature .

4. Safety requirements in emergency situations

4.1. In the event of an accident, the victim or an eyewitness who was at the same time is obliged to immediately notify the foreman or head of the site, who must organize the provision of first (pre-medical) aid to the victim and send him to a medical institution. In case of a severe accident, immediately call an ambulance and notify the administration.

4.2. Troubleshooting of electrical equipment of hoisting machines should be carried out only when the crane is disconnected from the mains.

5. Safety requirements at the end of work

5.1. At the end of a shift or work, the electrician must:

  • tidy up the workplace;
  • remove parts, materials, electrical equipment and tools;
  • tidy up the wiring diagrams and other technical documentation;
  • make an entry in the operational log on the technical condition of the electrical equipment of hoisting machines in the assigned area;
  • hand over to the electrician accepting the shift the technical documentation approved by the power engineer of the shop (site), safety protective equipment, make an entry on the handover of the shift in the operational log and sign the handover of the shift.

See other articles Section Occupational Safety and Health

 We recommend interesting articles Section Standard instructions for labor protection:

▪ Operation of an electric single-girder overhead crane. Standard instruction on labor protection

▪ Pruning with petrol-powered saws with low handles. Standard instruction on labor protection

▪ Work on insert-sewing-cutting machines. Standard instruction on labor protection

See other articles Section Standard instructions for labor protection.

Read and write useful comments on this article.

<< Back

Latest news of science and technology, new electronics:

Artificial leather for touch emulation 15.04.2024

In a modern technology world where distance is becoming increasingly commonplace, maintaining connection and a sense of closeness is important. Recent developments in artificial skin by German scientists from Saarland University represent a new era in virtual interactions. German researchers from Saarland University have developed ultra-thin films that can transmit the sensation of touch over a distance. This cutting-edge technology provides new opportunities for virtual communication, especially for those who find themselves far from their loved ones. The ultra-thin films developed by the researchers, just 50 micrometers thick, can be integrated into textiles and worn like a second skin. These films act as sensors that recognize tactile signals from mom or dad, and as actuators that transmit these movements to the baby. Parents' touch to the fabric activates sensors that react to pressure and deform the ultra-thin film. This ... >>

Petgugu Global cat litter 15.04.2024

Taking care of pets can often be a challenge, especially when it comes to keeping your home clean. A new interesting solution from the Petgugu Global startup has been presented, which will make life easier for cat owners and help them keep their home perfectly clean and tidy. Startup Petgugu Global has unveiled a unique cat toilet that can automatically flush feces, keeping your home clean and fresh. This innovative device is equipped with various smart sensors that monitor your pet's toilet activity and activate to automatically clean after use. The device connects to the sewer system and ensures efficient waste removal without the need for intervention from the owner. Additionally, the toilet has a large flushable storage capacity, making it ideal for multi-cat households. The Petgugu cat litter bowl is designed for use with water-soluble litters and offers a range of additional ... >>

The attractiveness of caring men 14.04.2024

The stereotype that women prefer "bad boys" has long been widespread. However, recent research conducted by British scientists from Monash University offers a new perspective on this issue. They looked at how women responded to men's emotional responsibility and willingness to help others. The study's findings could change our understanding of what makes men attractive to women. A study conducted by scientists from Monash University leads to new findings about men's attractiveness to women. In the experiment, women were shown photographs of men with brief stories about their behavior in various situations, including their reaction to an encounter with a homeless person. Some of the men ignored the homeless man, while others helped him, such as buying him food. A study found that men who showed empathy and kindness were more attractive to women compared to men who showed empathy and kindness. ... >>

Random news from the Archive

First successful robotic liver transplant 19.07.2023

Transplant surgeon Dr. Adil Khan and his team performed the first robotic liver transplant in the US at Barnes-Jewish Hospital. Now this innovative procedure is planned to be introduced in other clinics.

A 60-year-old patient suffering from liver cancer and cirrhosis caused by hepatitis C underwent a successful operation using advanced robotic equipment, while the chief surgeon controlled the operation from a nearby console.

"The transplant was a success: the new liver began to function immediately and the patient made a full recovery without complications," said Dr. Adil Khan, who led the surgical team from the University of Washington School of Medicine at Barnes-Jewish Hospital.

The recipient felt comfortable and regained mobility within a month after the operation, expressing a desire to return to golf and swimming. It usually takes about six weeks to recover from such an operation.

The hospital has focused on developing cutting-edge technology to minimize the invasiveness of operations and speed up patient recovery. Surgeons have already successfully completed more than 30 kidney transplants and other bile duct, pancreas and stomach related procedures using the robotic system. However, this operation was the first robotic liver transplant in the United States.

Liver transplantation is one of the most complex abdominal surgeries. Usually, the surgeon needs two incisions - 10 and 40 cm. However, in this case, the surgeons managed to get by with only 1,5 and 15 cm incisions.

The duration of the operation was a little over eight hours, but surgeons believe that the time of the operation will decrease as the procedure becomes more widespread and improved.

Other interesting news:

▪ Internet by rope

▪ Netgear Nighthawk M1 Mobile Router

▪ Global warming will open up the North Pole for navigation

▪ Wall mounted smart battery for home

▪ Seed Bank in the Arctic

News feed of science and technology, new electronics

 

Interesting materials of the Free Technical Library:

▪ section of the site Big encyclopedia for children and adults. Selection of articles

▪ article Don't think down the seconds. Popular expression

▪ article Over what three seas did the Tver merchant Afanasy Nikitin travel? Detailed answer

▪ article The main directions in the work on labor protection

▪ article Noise suppression surge protector. Encyclopedia of radio electronics and electrical engineering

▪ article Simple power supply, 5 volts 0,5 amperes. Encyclopedia of radio electronics and electrical engineering

Leave your comment on this article:

Name:


Email (optional):


A comment:




Comments on the article:

a guest
You are great [up]


All languages ​​of this page

Home page | Library | Articles | Website map | Site Reviews

www.diagram.com.ua

www.diagram.com.ua
2000-2024