Instructions on labor protection when dismantling buildings and structures

Occupational Safety and Health

Occupational Safety and Health / Standard instructions for labor protection

Comments on the article Comments on the article

Safe Operation

1. General requirements for labor protection

1.1. This instruction has been revised in accordance with SNIP 12-03-99 Safety in construction, taking into account changes and additions, the standards of the State Standard of Russia and the Ministry of Labor of Russia.

1.2. High-risk work includes work in the performance of which there is or may arise an occupational hazard, regardless of the nature of the work. In the production of these works, in addition to the usual safety measures, it is necessary to carry out additional measures developed separately for each specific production operation.

1.3. The list of jobs and professions that are subject to additional (increased) safety requirements should be specified in the order for the enterprise separately.

1.4. Work on dismantling buildings and structures should be carried out only with a permit and after conducting targeted instruction directly at the workplace.

Responsibility for the implementation of measures to ensure the safety of work lies with the heads of enterprises.

1.5. When organizing work (location of work sites, workplaces, production facilities, walkways, sanitary facilities), zones dangerous to people should be established within which dangerous and harmful production factors constantly operate or may arise.

1.6. The zones of permanent hazardous production factors should include workplaces, passages and passages to them, located:

  • near uninsulated current-carrying parts of electrical installations;
  • closer than 2 m of unenclosed differences in height by 1,3 m or more;
  • in places where harmful or dangerous substances are contained in concentrations above the MPC or there are dangerous and harmful physical factors with parameters above the MPC.

1.7. The zones of potentially hazardous production factors should include unprotected and unprotected:

  • land plots near the building under construction;
  • floors of buildings and structures in one grip, on which work is carried out (assembly, dismantling, repair of structures or process equipment);
  • zones of movement of machines, mechanisms, technological equipment or their parts, assemblies, parts, working bodies.
  • areas over which cargo is moved by cranes.
  • areas where equipment is located with poisonous, aggressive, flammable liquids, etc., as well as areas where the contractor's personnel may be exposed to hazardous and harmful factors.

1.8. Before starting work in hazardous areas, organizational and technological measures should be taken to ensure the safety of workers, and work should be performed only with a work permit.

1.9. In order to prevent access by persons not related to the performance of work in hazardous areas, before starting work, it is necessary to install protective or signal fences in accordance with the requirements of GOST 23407-78 and inventory fences of construction sites and areas for construction and installation works.

1.10. Performance of work in hazardous areas is allowed only if there is a project for the production of works (PPR) or technological maps containing specific solutions for protecting workers from exposure to hazardous and harmful production factors.

1.11. The following persons are allowed to independently carry out work on dismantling buildings and structures:

  • not younger than 18 years old;
  • recognized as fit for their production by the medical commission;
  • having a work experience in the specified works for at least one year and a tariff category not lower than the 3rd level;
  • trained and tested knowledge of the rules, norms and instructions for labor protection, including this instruction;
  • having a certificate for the right to carry out these works;
  • who have been instructed at the workplace on safety during the performance of work.

1.12. Workers who are first admitted to work on dismantling buildings and structures for one year must also perform work under the direct supervision of experienced workers appointed for this by order of the organization.

2. Labor protection requirements before starting work

2.1. Before starting work, a work permit is issued in 2 copies. The right to issue work permits is granted to specialists authorized to do so by order of the head of the organization.

2.2. The specialists of the organization who have passed the test of knowledge of the rules and norms of labor protection and this briefing should be appointed as responsible managers of the work.

2.3. Foremen, foremen who have been trained and tested knowledge of safety regulations, fire safety rules for this manual may be appointed as responsible executors of work.

2.4. The responsible performer of the work is responsible for the safe performance of work, the observance by the members of the brigade of the safety measures specified in the work permit, the mandatory use of PPE.

2.5. From the moment the team is allowed to work on dismantling buildings and structures, the responsible performer of the work must be at the workplace and constantly supervise the work of the team members and the implementation of safety measures.

2.6. When performing work on dismantling buildings and structures, the team must consist of at least two people, including the responsible person.

2.7. Brigadiers, team leaders, workers are allowed to perform high-risk work on the territory of an operating enterprise; before admission, they must receive targeted instruction with the involvement of responsible employees of the enterprise on whose territory the work is to be performed.

2.8. The issuance and return of permits is registered in the logbook for recording and issuing permits for high-risk work. The magazine, blank forms and closed work orders must be kept by the person issuing them.

2.9. Check the implementation of the security measures provided for by the work permit.

2.10. Conduct targeted safety briefings to team members at the workplace.

2.11. Indicate to each member of the brigade his workplace.

2.12. When performing hot work, issue a separate work permit, present the preparation of the workplace to the responsible employee of the fire supervision.

2.13. Before starting demolition work, it is necessary;

  • determine the method of demolition of the building, the availability of drawings;
  • make sure there are no people in the building to be demolished;
  • disconnect all communications and electrical wiring;
  • remove LVZh and GZh.

3. Labor protection requirements during work

3.1. The responsible manager is constantly at the work site and monitors the implementation by team members of safety measures and the technological sequence of the demolition work

3.2. It is prohibited to leave structures in a condition where they could be destroyed by wind or vibration.

3.3. Foundation walls that serve as retaining walls to support soil or adjacent buildings should not be demolished until adjacent buildings are equipped with temporary wall support devices or stiffeners and the soil is removed or secured with sheet piling or formwork.

3.4. When using bulldozers or excavators to demolish buildings, the nature of the buildings, their size, and the power of the equipment used should be taken into account.

3.5. When using explosives for demolition of buildings, it is necessary to timely coordinate measures for protection against blast waves, as well as safe distances.

3.6. When using a ball for demolition of buildings, a safe zone at least 1,5 m wide of the height of the building or structure must be installed around the impact points.

3.7. When dismantling floors for the movement of workers, boards or bridges must be laid.

3.8. When dismantling steel structures, it is necessary to take all possible measures to avoid the danger associated with sudden twisting, bending, and destruction of prefabricated steel and iron structures; dismantling is carried out in tiers.

3.9. Prohibit members of the brigade from leaving the work area without permission, to perform work not provided for by the work permit.

3.10. To withdraw the members of the brigade from the place of work for the duration of breaks during the work shift, while the work permit remains with the responsible performer of the work. Resume work after a break, only personally inspecting the workplace.

4. Labor protection requirements in emergency situations

4.1. If equipment defects are found that pose a danger to human life and the integrity of the equipment, immediately stop work, if possible, disconnect the electrical equipment from the mains (if any), take measures to eliminate the accident, and report the incident to the manager.

4.2. If there is a danger of an accident, take measures to prevent it. If an accident occurs, provide first aid to the victim, if necessary, call an ambulance.

4.3. In the event of a fire, immediately call the fire brigade, take people to a safe place and, if possible, remove combustible substances, start extinguishing the fire with primary fire extinguishing equipment, extinguishing with dry sand or a carbon dioxide fire extinguisher. Report the fire to the manager.

5. Labor protection requirements at the end of work

5.1. At the end of the work, remove the team from the place of work. The completion of work is formalized by signatures in the work permit and this order is transferred to the responsible work manager.

Application. Features of the organization and safe production of combined work

1. Combined are construction and installation works that are carried out on the same site, object (building) simultaneously by several organizations (divisions), while their working areas are in contact or overlap one another.

2. Responsibility for the safe organization of joint work in general throughout the entire construction and installation complex rests with the heads of the general contractor.

3. The head of the general contracting organization is obliged to allocate and, by his order, assign sections of the entire construction area, as well as all objects, buildings, structures or parts of them under construction to the divisions of his organization.

The transfer to subcontractors of construction sites of parts of buildings, structures or individual objects for the performance of construction and installation works is formalized by a bilateral act between the general contractor and each subcontractor for the period of performance of these works.

4. The specified subdivisions and organizations in the areas, territories, buildings and structures assigned to them are charged with the obligation to perform the function of a general contractor for the organization and safe production of construction and installation works, as well as monitoring their implementation.

5. The heads of organizations performing the functions of a general contractor in the areas assigned to them are required to develop and agree with subcontractors on the schedule for the production of joint work, labor protection and fire safety measures that are mandatory for all organizations conducting work on this site.

6. Responsibility for the safe organization of combined work at the facility is assigned from the beginning of construction to the transfer of facilities under a bilateral act of a subcontractor - to the heads of departments of the general contractor. After signing a bilateral act of acceptance of the object or its part - to the head of the subcontractor.

7. After completion of work and transfer of the facility to permanent operation - to the head of the operating organization.

8. Responsibility for accidents that occurred with employees of organizations performing joint work is borne by the following officials of the organization:

The person who issued the work permit, if the activities indicated in it, did not ensure the safety of the workers.

Those who did not take the safety measures specified in the work permit.

Leading work on the work permit in the event that they expand the scope of work beyond the limits established by the work permit.

In which the victim works, if the combined work was carried out by this organization without a work permit.

9. The work permit for the performance of combined work in the areas assigned to subcontracting organizations must be issued by responsible employees of these organizations.

 We recommend interesting articles Section Standard instructions for labor protection:

▪ Dressing room nurse. Standard instruction on labor protection

▪ RTU station equipment electrician. Standard instruction on labor protection

▪ A mechanical assembly worker fixing a frame with a spring set. Standard instruction on labor protection

See other articles Section Standard instructions for labor protection.

Read and write useful comments on this article.

<< Back

Latest news of science and technology, new electronics:

Artificial leather for touch emulation 15.04.2024

In a modern technology world where distance is becoming increasingly commonplace, maintaining connection and a sense of closeness is important. Recent developments in artificial skin by German scientists from Saarland University represent a new era in virtual interactions. German researchers from Saarland University have developed ultra-thin films that can transmit the sensation of touch over a distance. This cutting-edge technology provides new opportunities for virtual communication, especially for those who find themselves far from their loved ones. The ultra-thin films developed by the researchers, just 50 micrometers thick, can be integrated into textiles and worn like a second skin. These films act as sensors that recognize tactile signals from mom or dad, and as actuators that transmit these movements to the baby. Parents' touch to the fabric activates sensors that react to pressure and deform the ultra-thin film. This ... >>

Petgugu Global cat litter 15.04.2024

Taking care of pets can often be a challenge, especially when it comes to keeping your home clean. A new interesting solution from the Petgugu Global startup has been presented, which will make life easier for cat owners and help them keep their home perfectly clean and tidy. Startup Petgugu Global has unveiled a unique cat toilet that can automatically flush feces, keeping your home clean and fresh. This innovative device is equipped with various smart sensors that monitor your pet's toilet activity and activate to automatically clean after use. The device connects to the sewer system and ensures efficient waste removal without the need for intervention from the owner. Additionally, the toilet has a large flushable storage capacity, making it ideal for multi-cat households. The Petgugu cat litter bowl is designed for use with water-soluble litters and offers a range of additional ... >>

The attractiveness of caring men 14.04.2024

The stereotype that women prefer "bad boys" has long been widespread. However, recent research conducted by British scientists from Monash University offers a new perspective on this issue. They looked at how women responded to men's emotional responsibility and willingness to help others. The study's findings could change our understanding of what makes men attractive to women. A study conducted by scientists from Monash University leads to new findings about men's attractiveness to women. In the experiment, women were shown photographs of men with brief stories about their behavior in various situations, including their reaction to an encounter with a homeless person. Some of the men ignored the homeless man, while others helped him, such as buying him food. A study found that men who showed empathy and kindness were more attractive to women compared to men who showed empathy and kindness. ... >>

Random news from the Archive

Oxygen stops aging 26.11.2020

Hyperbaric oxygen therapy is used for decompression sickness, carbon monoxide poisoning, injuries that led to severe blood loss, burns, and severe infections (although its effectiveness has not yet been confirmed in all cases). The essence of the procedure is that the patient is in a chamber (pressure chamber) with a pressure that is higher than normal atmospheric pressure. Under such conditions, the blood is better saturated with oxygen - it is carried not only by erythrocytes, but also to a large extent by blood plasma.

Researchers at Tel Aviv University have found that telomeres lengthen in human immune cells after hyperbaric oxygen therapy. So called end sections of chromosomes, in which no genetic information is encoded. Their job is to protect the rest of the chromosome from damage. Telomeres shorten over time, and the shorter it is, the greater the likelihood of various age-related anomalies. Therefore, they are called one of the indicators of aging.

On the other hand, cells have an enzyme that can lengthen telomeres, but this enzyme is usually inactive. Saturation of the blood with oxygen, apparently, somehow activates it. The experiments were carried out with 35 volunteers over 64 years of age - within three months they underwent 60 sessions of hyperbaric oxygen therapy. As a result, telomeres in immune blood cells lengthened by 20-38%. That is, oxygenation not only stopped aging, but also reversed it - at least in these cells.

In the blood, the proportion of aged cells decreased by 11-37%. We have already talked about such cells: despite all the aging processes, the program of cellular self-destruction does not turn on in them, as it should be in the norm. As a result, the cell, having grown old, continues to live and age even deeper, and at the same time it releases various substances that spoil the life of other cells. Animal experiments have shown that if the body is cleansed of aged cells, it prevents some age-related diseases and prolongs life.

A lot depends on our immune system. Perhaps with the help of hyperbaric oxygen therapy, which rejuvenates it, we will be able to do what we do with mice: delay age-related diseases and increase life expectancy. Although all the same, sooner or later it is necessary to find out the mechanism that links rejuvenation with an increased level of oxygen in the blood.

Other interesting news:

▪ The moon got brighter, the sun dimmed

▪ Good cholesterol protects the liver from inflammation

▪ Method of non-surgical treatment of neurological diseases

▪ Ultra Low Gravity Measurement

▪ Effect of stress on brain structure

News feed of science and technology, new electronics

 

Interesting materials of the Free Technical Library:

▪ section of the site Consumer Electronics. Selection of articles

▪ article What we have, we do not store, having lost, crying. Popular expression

▪ article What is a gentleman's agreement? Detailed answer

▪ article Dog parsley. Legends, cultivation, methods of application

▪ article The original wow-prefix. Encyclopedia of radio electronics and electrical engineering

▪ article DRV-0,1 electric motor in a tape recorder. Encyclopedia of radio electronics and electrical engineering

Leave your comment on this article:

Name:


Email (optional):


A comment:




Comments on the article:

Maksim
Good instruction. [lol]


All languages ​​of this page

Home page | Library | Articles | Website map | Site Reviews

www.diagram.com.ua

www.diagram.com.ua
2000-2024